1
Chapter 1 Overview
1.1 Preparation
1)
Cut a slot from the floor with a proper tool. The depth and width should be approximately
100mm and 30mm.
2)
Put the wire through the pipe.
3)
In order to avoid the impact on communication, 220V/110V power line (high voltage) and signal
line (low voltage) should be separated. The ground wire must be connected.
SBT1000S series appearances and sizes as shown in Figure 1-1
Figure 1-1
Chapter 2 Installation
2.1 Before the installation, it is necessary to check the device first:
1)
Connect the wires to power supply.
2)
Open the air switch to test whether the device is working properly, wait for 10 seconds for the
gate to complete self-test program. If everything is normal, you can start the installation
procedures. If an exception occurs, please contact your vendor for information.
2.2 Cables installation
For the outlets of the concealed cables, please refer to the drawing showing the mounting holes.
The input voltage for this swing barrier turnstile is AC100-120V/200-240V. Note that the PVC conduits
are buried 100mm below the ground, with the height of the exposed part more than 100mm.As
shown in Figure 2-2.