Zeus Technology Co., Ltd. Shenzhen
8
Prompted interface prompts:
1, first start the car, the car starts to wait for about 15 seconds, to ensure
stable operation of the engine has been
2, press <Enter> to start testing, enter the test screen (Figure 3.3.1)
3, the engine speed is gradually increased to 2000r / min. The device records
the minimum and maximum charging voltage value in this process.
4, the end of the test, reading the test results.
Test Data Analysis
1, the voltage is normal charging system is 13.3 ~ 15 v.
Two, if more than 15 v, please check the car's regulator. If less than 13 v,
please check the connections, lines and alternators.
Note
: If the 24v system, the reference voltage value can be multiplied by
two.
test result print operations can refer battery test results printing
operation.
d.Maximum load test
In the main menu (Figure 3.1.0) Select option 4 (maximum load test), and press
<Enter> key to enter the maximum load test operation prompt interface (Figure
3.2.0 below).
Follow the prompts, first open all the electrical equipment, and then start the
engine after waiting for about 15 seconds waiting for the stable operation of the
engine press <Enter> to start testing, intrusion detection interface (Figure 3.4.1).
Check the minimum voltage, if the minimum voltage <12.8V, then the load
may be a problem, check the generator belt, or whether there is a short circuit
wire.
图
3.4.0
图
3.4.1