background image

15

Hot water  
connections

Submittals and product literature 
detailing unit operation, controls 
and connections should be 
thoroughly reviewed before 
beginning the connection of the 
heating medium to the unit.

All shipped loose valve packages 
should be installed as required 
and all service valves should be 
checked for proper operation.

All coil and valve package 
connections are to be made 
with a sweat or solder joint. 
Care should be taken to assure 
that no components in the valve 
package are subjected to a high 
temperature which may damage 
seals or other materials. Many 
two-position electric control 
valves, depending on valve 
operation, are provided with a 
manual opening lever. This lever 
should be placed in the “open” 
position during all soldering 
or brazing operations. In 
accordance with good soldering 
and brazing practices, valve 
bodies should be wrapped with 
a wet rag to help dissipate the 
heat.

If the valve package connection 
at the coil is made with a union, 
the coil side of the union must be 
prevented from twisting during 
tightening to prevent damage to 
the coil tubing. Over-tightening 
must be avoided to prevent 
distorting the union seal surface 
and destroying the union, 
ultimately causing a leak. 

Secure the union nut hand-tight 
and then tighten no more than an 
additional 1/4 turn. 

The inlet supply connection is 
marked at the appropriate coil 
stub-out with the other coil 
stub-out being the outlet return 
connection. 

After the connections are 
completed, the system should 
be tested for leaks. Since 
some components are not 
designed to hold pressure with 
a gas, hydronic systems should 
be tested with water. Test 
pressure must not exceed 250 
psig. Pressure testing should 
be completed prior to sheet 
rocking, finished floors, painting, 
caulking, etc. 

All water coils must be protected 
from freezing after initial filling 
with water. Even if the system is 
drained, unit coils may still hold 
enough water to cause damage 
when exposed to temperatures 
below freezing.

In the event that leaking or 
defective components are 
discovered, the Zehnder Rittling 
Sales Representative must be 
notified before any repairs are 
attempted. All leaks should be 
repaired before proceeding with 
the installation.

After system integrity has been 
established, it is recommended 
that the piping be insulated in 
accordance with the project 
specifications. This is the 
responsibility of the installing 
or the insulation contractor. 
Zehnder Rittling will not accept 
any charges associated with 
re-insulating piping if the 
installing contractor failed to 
establish system integrity prior to 
insulating. 

Hot water connections

Summary of Contents for RC-360

Page 1: ...i Cooling Fresh Air Clean Air Heating Rittling Cabinet Unit Heater Installation Operation and Maintenance ...

Page 2: ...ng 11 Safety considerations 12 Unpacking and preparation 13 Handling and installation 14 Hot water connections 15 Ductwork connections 16 Electrical connections 17 Wiring diagram 18 Start up 20 Air system balancing 21 Heating system 21 Water system balancing 22 Water treatment 22 Controls operation 23 Exposed unit touch up 23 Normal operation maintenance 24 Replacement parts 26 Equipment start up ...

Page 3: ... 300 RW Wall RW 260 shown RW 270 and RW 280 available RWI Wall inverted flow RWI 290 shown RWI 300 and RWI 310 available RRW Wall partially recessed RRW 320 shown RRWI Wall partially recessed inverted flow RRWI 330 shown RFRW Wall fully recessed RFRW 340 shown RFRWI Wall fully recessed inverted flow RFRWI 350 shown Models and arrangements 1 ...

Page 4: ...FI 240 RS 200 RSI 240 RF 220 RFI 250 RF Floor RF 200 shown RF 220 available RC Ceiling RC 360 shown RC 370 RC 380 RC 390 and RC 400 available RFI Floor inverted flow RFI 240 shown RFI 250 available RS Floor sloped RS 200 shown RRC Ceiling partially recessed RRC 440 shown RFRC Ceiling fully recessed RS 200 shown RSI Floor sloped inverted flow RSI 240 shown 2 ...

Page 5: ...2 Cu Blower Quantity 1 1 2 2 1 2 4 4 Diameter 5 7 5 7 5 7 5 7 5 7 5 7 5 7 Width 7 5 10 4 7 5 10 4 7 5 10 4 7 5 10 4 Filter Number 1 1 1 1 1 1 1 Length in 22 28 34 46 52 60 70 Width in 9 75 9 75 9 75 9 75 9 75 9 75 9 75 Thickness in 1 1 1 1 1 1 1 Cabinet size Height in 26 5 26 5 26 5 26 5 26 5 26 5 26 5 Length in 38 2 44 2 50 2 62 2 68 2 76 2 86 2 Width in 10 10 10 10 10 10 10 Shipping weight lbs 8...

Page 6: ...40 Power input Watts 100 110 130 180 325 368 368 Voltage Volts 120 120 120 120 120 120 120 Hz 60 60 60 60 60 60 60 Phase 1 1 1 1 1 1 1 Table B Electrical ratings Notes Maximum circuit ampacity MCA 1 25 x FLA motor 1 FLA motor 2 FLA electric heat Maximum overcurrent protection MOP 2 25 x FLA motor 1 FLA motor 2 FLA electric heat If the calculated MOP is within 10 of the next smaller available fuse ...

Page 7: ... 2 3 1 2 5 1 4 4 1 2 8 1 8 RF 200 shown Dimensional data Unit size A B C D 02 38 3 16 22 3 16 24 20 03 44 3 16 28 3 16 30 26 04 50 3 16 34 3 16 36 32 06 62 3 16 46 3 16 48 44 08 68 3 16 52 3 16 54 50 10 76 3 16 60 3 16 62 58 12 86 3 16 70 3 16 72 68 Notes 1 and 2 row coil supply and return 1 2 nominal 5 8 OD all sizes Inlet grille optional Unit shown with left hand piping connections and right han...

Page 8: ...S 200 shown Dimensions and data Models RS and RSI Dimensional data Unit size A B C D 02 38 3 16 22 3 16 24 20 03 44 3 16 28 3 16 30 26 04 50 3 16 34 3 16 36 32 06 62 3 16 46 3 16 48 44 08 68 3 16 52 3 16 54 50 10 76 3 16 60 3 16 62 58 12 86 3 16 70 3 16 72 68 Notes 1 and 2 row coil supply and return 1 2 nominal 5 8 OD all sizes Inlet grille optional Unit shown with left hand piping connections and...

Page 9: ...urn and 1 row steam supply 1 row hot water suppy and 1 row steam return 2 row hot water return 2 row hot water supply 2 row hot water return 7 3 8 8 1 8 2 row hot water supply 7 1 4 4 1 2 24 24 18 1 4 16 1 2 15 3 4 13 1 2 1 row hot water supply and 1 row steam return Filter position 10 3 8 2 5 1 4 7 1 4 2 5 1 4 4 1 2 5 5 8 Dimensions and data Notes 1 and 2 row coil supply and return 1 2 nominal 5 ...

Page 10: ...nd 2 row coil supply and return 1 2 nominal 5 8 OD all sizes Unit shown with left hand piping connections and right hand electrical connections as standard Right hand piping connections with left hand electrical connections available as an option Piping hand determined when facing the air outlet All listed dimensions are approximate and are subject to change without notice Modifications to the pro...

Page 11: ...03 44 3 16 28 3 8 30 18 5 8 04 50 3 16 34 3 8 36 23 5 8 06 62 3 16 46 3 8 48 23 5 8 08 68 3 16 52 3 8 54 33 5 8 10 76 3 16 60 3 8 62 33 5 8 12 86 3 16 70 3 8 72 33 5 8 Notes Damper motor always on right side when viewing unit from front side All listed dimensions are approximate and are subject to change without notice Modifications to the product specifications must be accepted by Zehnder Rittlin...

Page 12: ...louvered inlet grille with internal bug screen 3 1 2 A Front View Weep holes 2 5 8 4 to 8 1 2 2 13 16 Side View Dimensions and data Outside air wall box Dimensional data Model A Rough opening WB 0203 24 22 1 2 x 3 WB 0406 29 27 1 2 x 3 WB 081012 39 37 1 2 x 3 10 ...

Page 13: ...d damage not discovered during unloading must be reported to the shipping company within 15 days of receipt of the shipment All units are shipped F O B factory Therefore Zehnder Rittling is not responsible for damage during transit It is the responsibility of the installing contractor to inspect and verify that the units shipped were in fact the correct model number voltage etc Any discrepancies s...

Page 14: ...ays pressure test with an inert fluid such as water or dry nitrogen to avoid possible damage or injury in the event of a leak or component failure during testing Always protect adjacent flammable material when welding or soldering Use a suitable heat shield material to contain sparks or drops of solder Have a fire extinguisher readily available Please follow standard safe practices regarding the h...

Page 15: ...ive environments or in locations subject to temperature or humidity extremes e g attics garages rooftops etc Corrosive conditions and high temperature or humidity can significantly reduce system performance reliability and overall service life a clean dry area of the building or in a warehouse Do not remove any equipment from its shipping package until it is needed for installation The equipment i...

Page 16: ...kets where hanging rod and rubber in shear or spring vibration isolators supplied by others can be used for proper suspension and vibration isolation The type of mounting device is a matter of choice however the mounting point should always be that provided in the chassis or cabinet Improper mounting could result in the unit falling from its position causing personal injury or even death After mou...

Page 17: ...using a leak Secure the union nut hand tight and then tighten no more than an additional 1 4 turn The inlet supply connection is marked at the appropriate coil stub out with the other coil stub out being the outlet return connection After the connections are completed the system should be tested for leaks Since some components are not designed to hold pressure with a gas hydronic systems should be...

Page 18: ...ovided with outside air should have some form of low temperature protection to prevent coil s from freezing This protection may be a low temperature thermostat to close the outside air damper a preheat coil to temper the outside air before it reaches the unit or any other protective method It should be noted that none of these methods will adequately protect a coil in the event of power failure Th...

Page 19: ...agram Failure to do so could result in personal injury or damage to components and will void the manufacturer warranty All wiring connections should be checked prior to start up to ensure connections have not come loose during shipment or installation minimizing problems during start up The fan motor s should never be controlled by any wiring or device other than the factory supplied switch or the...

Page 20: ...ELLOW WHITE YELLOW RED RED BLACK BLACK B R YEL WALL THERMOSTAT OPTIONAL RETURN AIR FAN CONTROL OPTIONAL AQUASTAT FAN CONTROL OPTIONAL R B WHITE BLACK GREEN WALL PLUG OPTIONAL DISCONNECT SWITCH OPTIONAL FREEZESTAT OPTIONAL M2 L2 YELLOW SEE CHART SEE CHART SEE CHART PSC MOTOR OPTION NOTE FOR HIGH STATIC MOTORS USE THE FOLLOWING 3 SPEED SWITCH WIRING CONFIGURATION RED LOW BLUE MED BLACK HIGH YELLOW W...

Page 21: ...L M BLOWER MOTOR MOTOR QUICK CONNECT OPTIONAL HEATER L1 T1 L2 T2 MANUAL MOTOR STARTER OPTIONAL TRANSFORMER L2 M2 FREEZESTAT OPTIONAL BLACK BLACK BLACK WHITE SEE CHART SEE CHART SEE CHART PSC MOTOR OPTION NOTE FOR HIGH STATIC MOTORS USE THE FOLLOWING 3 SPEED SWITCH WIRING CONFIGURATION RED LOW BLUE MED BLACK HIGH YELLOW COMPLETE THE WIRING IN ACCORDANCE WITH NATIONAL AND LOCAL CODES WIRING DIAGRAM ...

Page 22: ...lancing The initial step is to visually inspect all of the equipment plenums connecting ductwork and piping Ensure that all systems are properly installed and supported and that all construction debris or foreign objects have been removed from the equipment Each unit should be checked for Free blower wheel operation Loose wires Loose or missing access panels or doors Filter installed clean and of ...

Page 23: ... some systems may require repeated venting over time to fully eliminate air in the system Prior to the water system start up and balancing the hot water system should be thoroughly flushed to clean out dirt and debris which may have accumulated in the piping during construction During this procedure all unit service valves must be in the closed position This will prevent any foreign material from ...

Page 24: ...expert The system must be complete and all components must be in operating condition before beginning the water system balancing procedures Each hydronic system has different operating conditions depending on the devices and controls installed for the particular application The actual balancing technique may vary from one system to another After the proper system operation is established the appro...

Page 25: ...op coats involving an exothermic chemical process between two components such as epoxies and urethanes should be avoided All standard colors including primer can be painted over If the installing contractor chooses not to paint over the primer color the factory cannot match primer color on future orders potentially causing color match issues in the field Factory touch up spray paint may require a ...

Page 26: ...d increased power consumption Clean the coil at every inspection Units provided with the proper type of air filters replaced regularly will require less frequent coil cleaning Normal operation and periodic maintenance General Each unit on a project will have its own unique operating environment and conditions which dictate a maintenance schedule for that unit that may be different from other equip...

Page 27: ...ed in the unit instead of being disposed of when dirty The cleanable filters may be washed in hot soapy water and then set aside to dry before recharging and reinstalling Before replacing the filter it should be recharged with some type of entrapment film such as Film Car Recharging Oil The filter should be sprayed on both sides or submerged in the film to assure complete coverage The filter shoul...

Page 28: ... undamaged Unit received complete as ordered Unit arrangement and handing is correct Unit structural support is complete and correct Handling and installation Mounting grommets isolators are used Unit mounted level and square Proper access is provided for unit and accessories Proper overcurrent protection is provided Proper service switch disconnect is provided Proper hot water line sizes to unit ...

Page 29: ......

Page 30: ......

Page 31: ......

Page 32: ...der Rittling 100 Rittling Boulevard Buffalo NY USA 14220 T 716 827 6510 F 716 827 6523 sales zehnder rittling com www zehnder rittling com Zehnder Rittling May 2014 English subject to change without notice ...

Reviews: