-04-
B.
Integrated suspended ceiling method
1. Install the main body
Fix the main body to the booms(recommended boom M6, if necessary)
Use tape or the filling to seal the junction between the exhaust pipe and adaptor.
The exhaust pipe should have the tendency (1 degree to 2 degrees) down
towards outside.
2.Install the exhaust pipe
3.Install the front cover
4.The booms must be in the same level during installation, if there is any difference,
please use the adjustable nuts to do the adjustment.
a. Open the 4 screw covers, and use 4 screws to fix the front cover and main body.
Please check the following inspection points once above finished:
b. Whether the installation of the front cover is well fixed.
c. Whether any noise or shaken happen during operation.
1.screw
2.nut
3.washer
4.fixed hole for the machine
5.hooded nut
Plastic pipe
Nominal 4”
inner diameter>100mm
Aluminum pipe
Downdip 1-2
Tape or fillings
Adjustable nut
Summary of Contents for ZBHC8
Page 16: ... 15 ...