Transportation, installation and storage
HDK350_EN_01_2005-05-10
25
►
Secure the dryer on the lifting
or forklift truck against sliding
movements.
►
Transport the dryer to its
installation site.
Dryer on transportation pallet
Installing and anchoring
Installing
►
Remove the packaging of the dryer.
►
Attach suitable lifting gear to the stand profiles and cross beams.
Risk of tilting!
The dryer should only be transported in an upright position. However, this
means that the centre of gravity of the unit is located in the upper half of
the dryer, so that there is a serious risk that the unit might topple over.
When attaching the dryer to the lifting gear, observe its centre of gravity!
►
Position the dryer at its installation site.