Installation
System Installer must adhere to Article 820-40 of the NEC that provides guidelines for proper grounding and
specifies that the cable ground shall be connected to the grounding system of the building, as close to the point
of cable entry as possible.
Unpacking and Inspection
Each unit is shipped factory tested. Ensure all items are removed from the container prior to discarding any packing
material.
Thoroughly inspect the unit for shipping damage with particular attention to connectors and controls. If there is
any sign of damage to the unit or damaged or loose connectors contact your distributor immediately. Do not put
the equipment into service if there is any indication of defect or damage.
Hardware Installations and Connections
It is highly recommended that quality cables and connectors be used for all video and audio source
connections.
1.
The unit comes with HDMI, Component & Composite inputs. Connect the desired cable,
not included.
2.
Use a quality 75
Ω
coaxial cable with “F” connectors from the unit’s RF Output.
3.
Connect the included power adapter to the unit’s POWER plug.
4.
Connect the power cord to an appropriately rated AC power outlet.
Device Programming and Setup:
Connecting to the GUI Interface:
Factory Default IP: 10.1.10.200
1. Connect an Ethernet cable to the Remote Setup Port of the ZPro-B2 and to your PC/Laptop.
2. Modify your PC/Laptop’s IP address to 192.168.1.100.
3. Enter ‘10.1.10.200’ into your web browser.
4. Make all required parameter changes.
5. Save all changes.