7.

Install TXV equalizer line in 1/8” hole previously made in vapor
line. Equalizer line should not be bottomed out in the vapor line.
Insert equalizer line at least 1/4” in the vapor line. Braze equalizer
line making sure that tube opening is not brazed closed.

All connections to be brazed are copper-to-copper and should be
brazed with a phosphorous-copper alloy material such as Silfos-5 or
equivalent. DO NOT use soft solder.

Install the TXV bulb to the vapor line near the equalizer line, using the
two bulb clamps furnished with the TXV assembly. Ensure the bulb is
making maximum contact. Refer to TXV installation instruction for view
of bulb location.

a.

Bulb should be installed on a horizontal run of the vapor line if
possible. On lines under 7/8" OD the bulb may be installed on
top of the line. With 7/8" OD and over, the bulb should be
installed at the position of about 2 or 10 o'clock.

b.

If bulb installation is made on a vertical run, the bulb should
be located at least 16 inches from any bend, and on the tub-
ing sides opposite the plane of the bend. The bulb should be
positioned with the bulb tail at the top, so that the bulb acts as
a reservoir.

c.

Bulb should be insulated using thermal insulation provided to
protect it from the effect of the surrounding ambient tempera-
ture.

SECTION V: ELECTRICAL CONNECTIONS

GENERAL INFORMATION & GROUNDING

Check the electrical supply to be sure that it meets the values specified
on the unit nameplate and wiring label.

Power wiring, control (low voltage) wiring, disconnect switches, and
over current protection must be supplied by the installer. Wire size
should be sized per NEC requirements.

The complete connection diagram and schematic wiring label is located
on the inside surface of the unit service access panel.

FIELD CONNECTIONS POWER WIRING

1.

Install the proper size weatherproof disconnect switch outdoors
and within sight of the unit.

2.

Remove the screws at the bottom of the corner cover. Slide corner
cover down and remove from unit. See Figure 5.

3.

Run power wiring from the disconnect switch to the unit.

4.

Remove the service access panel to gain access to the unit wiring.
Route wires from disconnect through power wiring opening pro-
vided and into the unit control box.

5.

Install the proper size time-delay fuses or circuit breaker, and
make the power supply connections.

FIELD CONNECTIONS CONTROL WIRING

1.

Route low voltage wiring into bottom of control box. Make low volt-
age wiring connections inside the junction box per Figures 7-9.

2.

The complete connection diagram and schematic wiring label is
located on the inside surface of the unit service access panel.

3.

Replace the corner cover and service access panel that were
removed in Steps 2 and 4 of the “Field Connections Power Wiring”
section.

4.

All field wiring to be in accordance with national electrical codes
(NEC) and/or local-city codes.

5.

Mount the thermostat about 5 ft. above the floor, where it will be
exposed to normal room air circulation. Do not place it on an out-
side wall or where it is exposed to the radiant effect from exposed
glass or appliances, drafts from outside doors, or supply air grilles.

6.

Route the 24-volt control wiring (NEC Class 2) from the outdoor
unit to the indoor unit and thermostat.

NOTE: 

To eliminate erratic operation, seal the hole in the wall at the

thermostat with permagum or equivalent to prevent air drafts
affecting the operation of in the thermostat.

CFM SELECTION BOARD SETTINGS

For proper system operation the CFM Selection Board jumpers must be
set properly. 

Refer to the Tabular Data Sheet for the recommended air flow settings
for each size condensing unit.

Set the cooling speed per the instructions for the air handler or furnace
by selecting the correct COOL and ADJ taps. Verify the airflow using
the LED display on the CFM selection board.

The HUMIDISTAT jumper must also be removed if a dehumidistat is
installed.

 Dry nitrogen should always be supplied through the tubing while it
is being brazed, because the temperature is high enough to cause
oxidation of the copper unless an inert atmosphere is provided. The
flow of dry nitrogen should continue until the joint has cooled.
Always use a pressure regulator and safety valve to insure that only
low pressure dry nitrogen is introduced into the tubing. Only a small
flow is necessary to displace air and prevent oxidation.

 In all cases, mount the TXV bulb after vapor line is brazed and has
had sufficient time to cool.

All field wiring must USE COPPER CONDUCTORS ONLY and
be in accordance with Local, National, Fire, Safety, & Electrical
Codes. This unit must be grounded with a separate ground
wire in accordance with the above codes.

 FIGURE 5:  

Typical Field Wiring

 FIGURE 6:  

CFM Selection Board

CONTROL
WIRING

POWER
WIRING

CORNER
COVER

SERVICE
ACCESS
PANEL

CFM SELECTION BOARD

TAP SELECTION

D
C
B
A

D
C
B
A

COOL

HEAT

ADJ

DELAY

REMOVE FOR

HEAT PUMP

HUMIDISTAT

Summary of Contents for 15 SEER - CZE

Page 1: ...h if not avoided may result in minor or moderate injury It is also used to alert against unsafe practices and hazards involving only property dam age INSPECTION As soon as a unit is received it should...

Page 2: ...nches apart coil face to coil face If the unit is to be installed on a hot sun exposed roof or a black topped ground area the unit should be raised sufficiently above the roof or ground to avoid takin...

Page 3: ...d care must be taken to avoid sharp bends which may cause a restriction 2 The lines should be installed so that they will not obstruct service access to the coil air handling system or filter 3 Care m...

Page 4: ...er cap and with an allen wrench back out counter clockwise until valve stem just touches the chamfered retaining wall See Page 4 PRECAU TIONS DURING BRAZING SERVICE VALVE 13 Replace plunger cap finger...

Page 5: ...er supply connections FIELD CONNECTIONS CONTROL WIRING 1 Route low voltage wiring into bottom of control box Make low volt age wiring connections inside the junction box per Figures 7 9 2 The complete...

Page 6: ...HERMOSTAT E Y2 Y2 HUM BLU YEL YEL BLK RED 1 VARIABLE SPEED FURNACE 2 STAGE AIR CONDITIONER C Y1 R W O HUMIDISTAT CONTACTS OPEN ON HUMIDITY RISE JUMPER MUST BE IN POSITION HUMIDISTAT INSTALLED YES G C...

Page 7: ...the tabular data sheet if line length is greater than 15 feet 4 Total system charge item 1 item 2 item 3 5 Permanently stamp the unit data plate with the total amount of refrigerant in the system Use...

Page 8: ...lclean mix one part Coilclean to seven parts water Allow solution to remain on coil for 30 minutes before rinsing with clean water Solution should not be permitted to come in contact with painted surf...

Page 9: ...12 110 449 11 451 11 454 11 457 12 115 478 11 480 11 483 11 486 12 120 507 10 509 10 512 11 515 11 125 537 10 539 10 542 10 545 10 TABLE 4 15Z48AC Subcooling Charging Chart Outdoor Ambient Indoor Wet...

Page 10: ...LED Status LED Description Status LED Troubleshooting Information Green POWER Module has power Supply voltage is present at module terminals Red TRIP Thermostat demand signal Y1 is present but the com...

Page 11: ...66901 035 20393 001 Rev C 1204 Unitary Products Group 11 SECTION IX WIRING DIAGRAM FIGURE 10 Wiring Diagram...

Page 12: ...e without notice Printed in U S A 66901 035 20393 001 Rev C 1204 Copyright by York International Corp 2004 All rights reserved Supersedes 035 20393 001 Rev A 0704 Unitary 5005 Norman Product York OK G...

Reviews: