background image

66901 / 035-20393-001 Rev. C (1204)

4

Unitary Products Group

PRECAUTIONS DURING BRAZING SERVICE VALVE

Precautions should be taken to prevent heat damage to service valves
by wrapping a wet rag around it as shown in Figure 4. Also, protect all
painted surfaces, insulation, and plastic base during brazing. After braz-
ing, cool joint with wet rag.

The valve can be opened by removing the plunger cap and fully insert-
ing a hex wrench into the stem and backing out counter-clockwise until
valve stem just touches the chamfered retaining wall.

Connect the refrigerant lines using the following procedure:

1.

Remove the cap and Schrader core from both the liquid and vapor
service valve service ports at the outdoor unit. Connect low pres-
sure nitrogen to the liquid line service port.

2.

Braze the liquid line to the liquid valve at the outdoor unit. Be sure
to wrap the valve body with a wet rag. Allow the nitrogen to con-
tinue flowing. Refer to the Tabular Data Sheet for proper liquid line
sizing.

3.

Carefully remove the rubber plugs from the evaporator liquid and
vapor connections at the indoor coil.

4.

Braze the liquid line to the evaporator liquid connection. Nitrogen
should be flowing through the evaporator coil.

5.

Slide the grommet away from the vapor connection at the indoor
coil. Braze the vapor line to the evaporator vapor connection. After
the connection has cooled, slide the grommet back into original
position. Refer to the Tabular Data Sheet for proper vapor line siz-
ing.

6.

Protect the vapor valve with a wet rag and braze the vapor line
connection to the outdoor unit. The nitrogen flow should be exiting
the system from the vapor service port connection. After this con-
nection has cooled, remove the nitrogen source from the liquid fit-
ting service port.

7.

Replace the Schrader core in the liquid and vapor valves.

8.

Go to “SECTION IV” for TXV installation.

9.

Leak test all refrigerant piping connections including the service
port flare caps to be sure they are leak tight. DO NOT OVER-
TIGHTEN (between 40 and 60 inch - lbs. maximum).

NOTE: 

Line set and indoor coil can be pressurized to 250 psig with dry

nitrogen and leak tested with a bubble type leak detector. Then
release the nitrogen charge.

NOTE: 

Do not use the system refrigerant in the outdoor unit to purge or

leak test.

10. Evacuate the vapor line, evaporator, and the liquid line to 500

microns or less.

11.

Replace cap on service ports. Do not remove the flare caps from
the service ports except when necessary for servicing the system.

12. Release the refrigerant charge into the system. Open both the liq-

uid and vapor valves by removing the plunger cap and with an
allen wrench back out counter-clockwise until valve stem just
touches the chamfered retaining wall. See Page 4 "PRECAU-
TIONS DURING BRAZING SERVICE VALVE".

13. Replace plunger cap finger tight, then tighten an additional 1/12

turn (1/2 hex flat). Cap must be replaced to prevent leaks.

See "System Charge” section for checking and recording system
charge.

SECTION IV: INSTALLATIONS REQUIRING 

TXV

For installations requiring a TXV, the following are the basic steps for
installation. For detailed instructions, refer to the Installation Instructions
accompanying the TXV kit.

Install TXV kit as follows:

1.

First, relieve the holding charge by depressing the Schrader valve
located in the end of the liquid line.

2.

After holding charge is completely discharged, loosen and remove
the liquid line fitting from the orifice distributor assembly. Note that
the fitting has 

right

 

hand

 

threads

.

3.

Remove the orifice from the distributor body using a small diame-
ter wire or paper clip. Orifice is not used when the TXV assembly
is installed.

4.

After orifice is removed, install the thermal expansion valve to the
orifice distributor assembly with supplied fittings. Hand tighten and
turn an additional 1/8 turn to seal. Do not overtighten fittings.

5.

Reinstall the liquid line to the top of the thermal expansion valve.
Hand modify the liquid line to align with casing opening.

6.

Install the TXV equalizer line into the vapor line as follows:

a.

Select a location on the vapor line for insertion of the equal-
izer line which will not interfere with TXV bulb placement.

b.

Use an awl to punch through the suction tube and insert the
awl to a depth to achieve a 1/8” diameter hole.

 Dry nitrogen should always be supplied through the tubing while it
is being brazed, because the temperature is high enough to cause
oxidation of the copper unless an inert atmosphere is provided. The
flow of dry nitrogen should continue until the joint has cooled.
Always use a pressure regulator and safety valve to insure that only
low pressure dry nitrogen is introduced into the tubing. Only a small
flow is necessary to displace air and prevent oxidation.

This is not a backseating valve. The service access port has a
valve core. Opening or closing valve does not close service access
port.
 If the valve stem is backed out past the chamfered retaining wall,
the O-ring can be damaged causing leakage or system pressure
could force the valve stem out of the valve body possibly causing
personal injury.

 FIGURE 4:  

Heat Protection

The evaporator is pressurized.

 Do not connect manifold gauges unless trouble is suspected.
Approximately 3/4 ounce of refrigerant will be lost each time a stan-
dard manifold gauge is connected.

Never attempt to repair any brazed connections while the system is
under pressure. Personal injury could result.

Summary of Contents for 15 SEER - CZE

Page 1: ...h if not avoided may result in minor or moderate injury It is also used to alert against unsafe practices and hazards involving only property dam age INSPECTION As soon as a unit is received it should...

Page 2: ...nches apart coil face to coil face If the unit is to be installed on a hot sun exposed roof or a black topped ground area the unit should be raised sufficiently above the roof or ground to avoid takin...

Page 3: ...d care must be taken to avoid sharp bends which may cause a restriction 2 The lines should be installed so that they will not obstruct service access to the coil air handling system or filter 3 Care m...

Page 4: ...er cap and with an allen wrench back out counter clockwise until valve stem just touches the chamfered retaining wall See Page 4 PRECAU TIONS DURING BRAZING SERVICE VALVE 13 Replace plunger cap finger...

Page 5: ...er supply connections FIELD CONNECTIONS CONTROL WIRING 1 Route low voltage wiring into bottom of control box Make low volt age wiring connections inside the junction box per Figures 7 9 2 The complete...

Page 6: ...HERMOSTAT E Y2 Y2 HUM BLU YEL YEL BLK RED 1 VARIABLE SPEED FURNACE 2 STAGE AIR CONDITIONER C Y1 R W O HUMIDISTAT CONTACTS OPEN ON HUMIDITY RISE JUMPER MUST BE IN POSITION HUMIDISTAT INSTALLED YES G C...

Page 7: ...the tabular data sheet if line length is greater than 15 feet 4 Total system charge item 1 item 2 item 3 5 Permanently stamp the unit data plate with the total amount of refrigerant in the system Use...

Page 8: ...lclean mix one part Coilclean to seven parts water Allow solution to remain on coil for 30 minutes before rinsing with clean water Solution should not be permitted to come in contact with painted surf...

Page 9: ...12 110 449 11 451 11 454 11 457 12 115 478 11 480 11 483 11 486 12 120 507 10 509 10 512 11 515 11 125 537 10 539 10 542 10 545 10 TABLE 4 15Z48AC Subcooling Charging Chart Outdoor Ambient Indoor Wet...

Page 10: ...LED Status LED Description Status LED Troubleshooting Information Green POWER Module has power Supply voltage is present at module terminals Red TRIP Thermostat demand signal Y1 is present but the com...