INSTALLATION
RECEIVING
When the absorption chiller-heater is
delivered, inspect it for transit damage.
Should any damage have occurred, do
not proceed with installation until the
Yazaki distributor has been notified and
any required remedial actions have been
completed.
The MG-Series units are too large for
the typical fork lift. Special handling
procedures must be followed in order to
safely remove the unit from a covered
trailer. An open flat-bed trailer is
preferred for easiest delivery, but is not
always an option.
Remember to properly plan the route
to the installation site. Also, keep in mind
when choosing the site, the unit will
someday have to be replaced, so be
mindful
of
permanent
and
semi-
permanent barriers.
The unit typically must be pulled out of
a container or trailer and often must be
pulled into position on site. The frame of
the unit is specifically designed for the
forces due to horizontal pulling. Attach
cable or acceptable equivalent to the
frame only at the provided holes. No
other points should be used for horizontal
pulling.
Figure 3
– Horizontal Movement
Figure 4
– Hallway Clearances
Summary of Contents for AROACE CH-MG150
Page 4: ...4 EQUIPMENT DIMENSIONS Figure 1 MG150 Dimensions ...
Page 5: ...5 EQUIPMENT DIMENSIONS Figure 2 MG200 Dimensions ...
Page 6: ...6 INTERNAL WIRING DIAGRAM ...
Page 7: ...7 ...
Page 8: ...8 Table 2 Internal Wiring Diagram Legend KRCH relay has been replaced by the KCH relay ...
Page 12: ...12 INSTALLATION CLEARANCES Figure 7 Installation and Service Clearances ...