Installation and Operation Guide SOLECTRIA XGI 1000
DOCR-070733-F (2/22/2021)
Page 62 of 78
Figure 7-1 Firmware Update
Communication Commissioning
Once all inverters are installed and energized, the XGI communications can be commissioned. Before proceeding ensure
that the following conditions are met:
All inverters energized, (DC voltage)
All inverters are connected via Ethernet in a supported network topology
All gateway inverters are connected to the LAN with DCHP enabled
Internet access is available on the LAN (if applicable)
Connect to the Cluster
Connect to the desired Cluster over Ethernet or WiFi using a smart device. If connecting over Ethernet be sure not to
disrupt the daisy chain or star network, always connect to an inverter at the end of a chain.
INFO
✔
Don’t Break the Chain! When connecting to a Cluster over Ethernet during the commissioning process it is important
that the Cluster LAN remain intact. Always connect to an open port on one of the XGI inverters at the end of a daisy
chain as not to disconnect any inverters from the Cluster.
Verify Communication
On the Landing Page, verify that all expected inverters appear on the Inverter List. If inverters are missing, check wiring,
and ensure that all inverters have been powered on for a minimum of 10 minutes.