Installation and Operation Guide SOLECTRIA XGI 1000
DOCR-070733-F (2/22/2021)
Page 52 of 78
Startup
Mechanical Installation
Make sure the mounting bracket is securely installed and all fasteners are tightened to the torque specifications. See
Mounting the Inverter
.
Electrical Connections
Make sure all conductors are landed on the correct terminals.
Make sure all connections are tightened to torque specifications. See
AC Connections
and
DC Connections
.
Make sure the DC Switch on the inverter is in the “OFF” position.
Make sure the AC Switch on the inverter is in the “OFF” position.
Electrical Check
Make sure the AC circuit breaker is properly sized.
Test the AC voltage and confirm that it is within the normal operating range.
Check the AC phase rotation, must be Clockwise.
Test the polarity of DC inputs and confirm they are proper. See
DC Connections
.
Make sure the open circuit voltage of input strings is less than 1000VDC.
Startup Steps for a Single Inverter
WARNING
Electrical Shock Hazard: Installer may come into contact with components that have hazardous voltage and energy
potential.
PPE: Use proper safety equipment when energizing the inverter
INFO
✔
Quick Start Guide For more details regarding communication commissioning, see the communication Quick Start
Guide.
1.
Turn ON the site AC breaker for the inverter.
2.
Complete the connection of the input PV source circuits (close the fuse holders).
3.
Turn ON the AC switch on the inverter.
4.
Turn ON the DC switch on the inverter.
5.
Verify that the Status Panel illuminates Ready and neither Maintenance nor Power Fault is illuminated.
a.
If the LEDs do not match the description above, see
Maintenance and Troubleshooting
b.
Verify that the Status Panel illuminates Ready, Network and Communications, and Power.
6.
Connect to the gateway inverter’s WiFi network, XGI-00-006 (see
User Interface Overview
).