Pipe configuration illustrated below
:
System configuration (Example)
5.
OPERATIONS
After correct installation, turn on the power control switch to start the pump. Both
direction of the motor are suitable for the pump.
Make sure all the pipes are connected properly and no leakage before start the pump.
If source tank fluid level is higher than pump head the fluid should flow into pump
head automatically. In this case, start pump then the transporting should begin.
If pump was installed above the source tank, pump may not be able to suck fluid into
pump spontaneously. In this case a check valve should be installed.(Sucking head is
not a guarantee.)
To change the discharge rate, loosen the fix-nut then turn the flow regulator knob
while the pump is running.(Do not turn the flow regulator knob when pump is stop).
Set the indicator between 0-12mm(clockwise to reduce discharge rate and the
opposite to increase). When indicator monitor at “12”, the stroke is at full length,
when at “0”, stroke is 0 mm. stroke length. The pump discharge rate is relative to
the stroke length proportionally. (See page 7.).
Turn flow regulator knob for one circle(360 degrees) the knob move 1unit(mm) on
the indicator .
For a precise flow control, after installation user should run a calibration before use.