27
D.
INSTALLATION
General
– The control unit & Filter junction box are supplied with 5 meters cables
in flexible conduit.
The user must connect only the line supply cable through a PG-13.5 mm conduit.
Requirements
: 5 x 1-1.5mm supply cable.
1
. Connect the line supply cable (5 x 1-1.5mm) to the control unit terminals :
IMPORTANT
! 1x2-4amp protectors MUST protect line supply.
TB GND - GND Wire.
TB1 - N Natural wire.
TB2 - L1 Line phase supply.
TB3 - L2 Line phase supply.
TB4 - L3 Line phase supply.
Control board Filter Junction box
TB5 - Motor GND. wire.
TB5
TB6 - Motor U phase wire.
TB6
TB7 - Motor V phase wire.
TB7
TB8 - Motor W phase wire.
TB8
TB9 – SV flushing solenoid common.
(1)
TB9
TB10 – SV flushing solenoid , live
(2)
TB10
TB11 – DP switches common
(3)
TB11
TB12 – DP switch live
(4)
TB12
2. Motor synchronization
Motor synchronization must be carried out as follows :
Switch the
MAIN
switch to
START
position and Verify that
ON
(L1) indicator lit.
Press push button
FLUSH
momentarily and Verify that
FLUSH
indicator lights and
the motor activated simultaneously.
Check the motor axis rotation (Which drives the filter dirt collector) ,
The rotation must be at the same arrow label direction.
If not , switch the
MAIN
switch to
STOP
position , and exchange between
two of the Motor phase and check again.(e.g. Between motor connection to
TB 6
><
7 or TB 7
><
8 in the control board or in the filter junction box.)
AF9800