PolluCom
®
F/S C Heat/Cooling Meter
Installation and operating instructions
M H 1500 INT, Page 6
4. Check installation point again for correct flow
direction (arrow on the EAS), correct
installation of the EAS if necessary.
5. Unscrew the overflow cap (B) from the single-
pipe connector (A), remove the profile seal
(C1) from the EAS and clean both sealing
surfaces of the EAS (A1 and A2). (Fig. 5.2.1)
Fig. 5.2.1 Installation of F PolluCom
®
F/S C X
connector
6. Remove the protective cap from the threaded
connection (D1) of the PolluCom
®
F/S C
coaxial meter (D) and insert the supplied new
profile seal (C2) onto the sealing surfaces (A1
and A2) of the EAS. Do not use any additional
sealants under any circumstances! (Fig. 5.2.2)
Fig. 5.2.2 Installation of F PolluCom
®
F/S C X
measuring capsule
7. Grease the thread of the coaxial meter (D) and
screw it into the EAS until it comes to a firm
stop on the EAS. Only use a hook wrench for
this purpose.
8. Seal the coaxial meter together with the
single-tube connector by pulling the enclosed
sealing wire in one piece through the sealing
eyelets on the measuring capsule (D2) and
the EAS (D3), tighten it and secure it with the
enclosed self-lock seal. Fig. 5.2.3
Fig. 5.2.3: Sealing example
9. Install and seal temperature sensor(s)
according to Chapter 6.
10. Then open the shut-off valves and check the
entire installation site for leaks.
11. Then put the heating/cooling system back into
operation.
5.3 PolluCom
®
F/S C RI (Typ Ista)
1. Check installation for completeness. An
original Ista-EAS must be installed in the
return and a corresponding immersion sleeve
or ball valve in the flow. Caution: In
refrigeration systems, the supply is the colder
pipe and the return is the warmer pipe. The
counter to be installed must then be in the
PolluCom
®
F/S C X RI version with
appropriate adjustment. Please check. In
refrigeration systems, the supply is the colder
pipe and the return is the warmer pipe. It is
simply pulled off upwards and mounted
separately in a suitable place by means of the
supplied wall adapter. (Cable length approx.
30 cm.) Switch off the heating or its circulation
pump.
2. Close the shut-off valves located upstream
and downstream of the single-pipe adapter
(EAS).
3. Check installation point again for correct flow
direction (arrow on the EAS), correct
installation of the EAS if necessary.
4. Unscrew the overflow cap (B) from the single-
pipe connector (A) (SW 22 mm), remove the
seal (C1) from the EAS and clean both sealing
surfaces (A1 and A2) of the EAS.
(Fig. 5.3.1)
D2 Sealing eye on the
coaxial meter
D3 Sealing eye on EAS (A3)