14
Version 1 – GBR (11/05/2022)
D-502-0260
e)
Mount the base to the floor so that the anchor bolts are at the extreme positions of the anchor slots
for a possibility of later increasing of the curtain pre-blow. The curtain should be automatically
rotated outwards by 10°. Make the final rotation of the curtain pre-blow according to local
conditions.
f)
Re-tighten the base to the floor.
3.2.1.2.
Bottom curtain connection - from the floor - base
(curtain regulation at the bottom - at the
floor)
-
The base mounting procedure is the same as for the top connection (see Chapter 3.2.1.1.)
3.2.2.
Placing the curtain in the working position
3.2.2.1.
Top curtain connection - from the ceiling
(curtain regulation at the top - at the ceiling)
a)
Place - set the unpacked curtain in the working position
b)
Slide the curtain onto the base guide rails
c)
Secure the curtain to the base with 6 self-tapping screws
Ø
3.5x9.5
(included in the "BREEZE-BASE"
base package) against falling.
FIXED ATTACHMENT
ATTACHMENT
AT THE CENTRE
OF THE
THROUGH
HOLES FOR THE
POSSIBILITY OF
LATER
ROTATION
Fig. 9
THE
CONNECTING
PERIPHERY IS
FROM THE
TOP
Fig. 9