CHAPTER 2 INSTALLATION AND COMMISSION
2-1 NOTES FOR EQUIPMENT INSTALLATION
PAY ATTENTION TO SAFETY! BEWARE OF BEING BRUISED!
2-2 EQUIPMENT DEBUGGING
1. Open the packing case and check if the equipment appearance is damaged.
2. Counting the accessories according to the packing list.
3. Install the main body on a horizontal and stable workbench and remove the fixed trans-
port accessories.
4. Connect power line, gas supply system, spindle cooling system, processing cooling
system and vacuum system as required.
5. It is forbidden to transport the shell and the movable door when transporting the com-
plete machine; the baseboard of the complete machine should be transported.
6. It is forbidden to move the equipment by pushing or pulling its shell.
1.Turn on the equipment power switch
,
then the lights in the processing areas will be
lighted up and the system will start.
2. Double click the icon on the desktop to run XMill300.exe, as shown in the figure.
3. Click the “HOME” button to make all the axes mechanically back to the origin. When
the step is done, the button will display“origin”and being highlighted, which indicates the
“HOME” function is normal.
4. Switch to manual operation interface, as shown in the figure below.