9
6.
Cable Management
1)
Please use cable ties to tie up all the projector cables at the cable tie
clampswhich are located along the scissors arms.
2)
Please tie cables equally on both sides of the scissor arms to balance the weight.
3)
Make sure that the cables are long enough for the lift to go up and down.
4)
Please check that all the cables are out of the way of operation.
7.
Installation of Ceiling Cover:
1)
The ceiling cover is fixed to the underside of the lift which normally greater in
size and serve as platform to receive all types of ceiling materials.
2)
The ceiling cover is settled to flush with the false ceiling.
3)
A minimum opening of
825mmWx625mmD
on false ceiling is required for the
lift to travel.
4)
The ceiling cover should be attached to the base plate, below the lift.
5)
Please use the screws provided (
M5-12mm
) to fix the ceiling cover and the lift.
8.
Re-adjusting of the UP and DOWN limit:
CAUTION:
The UP and DOWN adjusting shall be done within 4 minutes. The motor is
equipped with a built-in thermal overload protector which limits their
operations to intermittent use only, the power supply will be cut off
temporarily if more than 4 minutes. If such things happen, please wait for
the motor to cool down and restart it again.
Summary of Contents for SC60
Page 1: ...0 Scissor Lift Model SC60 SC40 Installation Instructions...
Page 22: ...21...