6
Part Number
18143,
E, 01/28/2020
Installation
Installing the Display Unit (P1BR-S01-D/P1CR-S01-D & P2BS-S01D)
The Display Unit should be located at the instrument panel, so that the visible and audible
indicators may be easily observed.
Drill a 2-
1/16” hole to accommodate
the P1BR-S01-D/P1CR-S01-D Display Unit.
Drill a 2-
1/8” hole to accommodate the
P2BS-S01-D Display Unit.
Insert Display Unit into hole and secure with the provided threaded mounting nut. A Trim Ring is
available if needed.
NOTE
DO NOT MAKE ELECTRICAL CONNECTIONS AT THIS TIME. THEY WILL BE ADDRESSED IN A LATER
SECTION.
Installing the Solenoid Valve for LPG Applications
The Solenoid Valve should be mounted on the tank side of the LPG regulator, as close to the tank
as practical. The tank itself should be mounted outside the cabin or crew quarters to avoid the
possibility of gas accumulation due to a leak.
NOTE
TIGHTEN TO 12-13 FT/LBS. DO NOT OVER-TIGHTEN.
NOTE
ALL PIPING MUST BE CHECKED FOR LEAKS. USE SOAPY WATER SOLUTION ON ALL JOINTS. NEVER
USE A FLAME TO CHECK FOR LEAKS.
Routing Sensor Cable(s) (FS-
X01 CABLE XX’)
A 20 FT Sensor Cable is provided for each Propane Fume Sensor. The Sensor Cables should be
routed starting at the Display Unit, then to the pre-determined location of the Propane Fume
Sensor. Connect to the Display Unit using the attached quick-disconnect connectors. Take care
not to pinch, break, or cut the Sensor Cable or put too much stress on the connectors while
routing the cable. Secure the Sensor Cable with the appropriate hardware for the application.
NOTE
DO NOT CUT EXTENSION CABLE FOR ANY PURPOSE. DOING SO VOIDS THE PRODUCTS
WARRANTY. LONGER CABLES ARE AVAILABLE FROM 20 FT TO 100 FT.