PREINSTALLATION
Installation responsibilities
The following explains Xerox and customer responsibilities.
Table 1-20.
Installation responsibilities
Xerox
•
Install the hardware component of the XPMF/VMS interface.
•
Assist you, if necessary, in installing the software
component.
•
Provide the XPMF/VMS interconnect kit.
Customer
•
Arrange for telephone lines and modems to be installed, if
required by your interconnect configuration.
•
Verify kit contents to make sure all necessary items are
included.
•
Install the host-resident software component (part of the
XPMF/VMS kit provided by Xerox) onto the VMS system.
•
Obtain all necessary hardware and software to form the
selected connection solution.
•
Coordinate the installation steps that involve both DEC and
Xerox service organizations.
•
Produce specifications for XPMF/VMS during the
configuration of the printer.
•
Install any communications controller components needed
for the DEC VAX system that submits jobs to the LPS.
Installation requirements
Before installing the host-resident software, you must have the
following privileges and resources available:
•
SETPRV privilege, or CMKRNL, WORLD, and SYSPRV
privileges
•
Minimum of 1,000 blocks of free disk space during
installation; 500 blocks after installation.
Hardware requirements
Listed below are the three VAX/VMS systems that support the
VAX-resident print supervisor (symbiont) software and the
requirements for each.
Note: Appropriate communication cables and modems may be
required. Consult your sales representative.
XEROX 4050/4090/4450/4650 LPS INSTALLATION PLANNING
1-25