SECTION 6
PREVENTATIVE MAINTENANCE
PV-15208 Photovoltaic Inverter
Operation and Maintenance Manual
Copyright 2000, Xantrex Technologies Inc./Trace Technologies Corp.
DOCUMENT: 150919
6-2
TURN-ON PROCEDURE
Refer to Section 3 for a detailed first-time turn on procedure.
1. Remove any lockout devices from the isolation transformer circuit breaker and PV disconnect
switch.
2. Close the isolation transformer circuit breaker.
3. Close the AC disconnect (if present).
4. Close the PV array disconnect switch (if present).
5. Turn the on/off switch to the on position.
After a 15 second initialization period and a 5 minute wake up period, the PV-15208 will automatically
begin power tracking, given the PV voltage is greater than the PV start voltage setpoint.