background image

SECTION 3
INSTALLATION AND INITIAL TURN-ON

     PV-15208 Photovoltaic Inverter

Operation and Maintenance Manual

     Copyright 2000, Xantrex Technologies Inc./Trace Technologies Corp.

DOCUMENT:  150919

3-6

Verify the PV+, PV-, PV neutral (if array is bipolar), and PV
safety ground are isolated from each other. The PV safety
ground should be bonded to the enclosure ground stud. Re-
fer to system schematic in Section 7.

Verify all PV fuses are installed (if present).

Verify PV string diodes are wired properly (if present).

•   

 Verify proper PV voltage polarity at the PV string disconnect/

combiner boxes.

     Initial Power

•    

Close the isolation transformer circuit breaker.

Verify 208 VAC voltage across the AC disconnect.

Close the AC disconnect (if present).

With the DC disconnect switch opened (if present), close one
of the PV array string disconnect devices.

Carefully measure VDC at the PV disconnect switch. The
value should be the same as at the PV array string disconnect
device. It should also be positive.

Close the PV disconnect switch (if present).

Carefully measure VDC across TB1-1 and TB1-2 (PV +/-)
terminal block. The value should be the same as at the PV

INITIAL TURN ON PROCEDURE

The following procedures are intended to verify correct installation and proper operation of the PV-
15208. These steps are to be followed sequentially. Do not continue if any of the steps or results are
unclear. Refer to Section 4 for a detailed description of system operation. Refer to Section 5 for fault
condition descriptions and troubleshooting. Refer to Section 7 for detailed system schematics.

     Visual Inspection, Isolation Transformer

Verify the isolation transformer circuit breaker is open.

Remove the isolation transformer access panel.

If the inverter side of the isolation transformer is configured WYE, the neutral must be left floating.
The transformer neutral must not be connected to the utility side neutral, the transformer chassis, or
ground.

Verify the inverter 208 VAC conductors are connected to the isolation transformer.

Verify the utility conductors are properly connected to the isolation transformer.

     Visual Inspection, PV-15208

Insure AC and DC disconnect are opened (if present).

Insure PV array string disconnect switches are opened (if present).

Open the door of the enclosure, and inspect.

Verify all wire connections are tight.

Inspect the cables between the terminal blocks and the matrix driver board. All wire harnesses
should be snap-locked into their respective PCB headers.

     Visual Inspection, PV Array Wiring

DC TERMINAL

Summary of Contents for PV-15208

Page 1: ...E INSTRUCTIONS THIS MANUAL CONTAINS IMPORTANT INSTRUCTIONS FOR TRACE TECHNOLOGIES MODEL PV 15208 GRID TIED PHOTOVOLTAIC INVERTER THAT SHALL BE FOLLOWED DURING INSTALLATION AND MAINTENANCE OF THE PV 15...

Page 2: ...nitialTurnOnProcedure Section 4 Operation DescriptionofSystemOperation Operator Interface Panel LED and LCD ExampleofNormalSystemOperation Section 5 Troubleshooting General FaultConditionsandTroublesh...

Page 3: ...are provides for complete overall system control with a vari ety of protective and safety features MAJOR COMPONENTS The major components of the PV 15208 are identified in Drawing No 150921 Main Enclos...

Page 4: ...trols the bus board The DSP module is designed to the industry standard PC 104 specification and is used to perform the majority of the calculations needed to control the bus board The most significan...

Page 5: ...e i b m A m u m i x a M C 0 5 y t i d i m u H e v i t a l e R g n i s n e d n o c n o N 5 9 o T n o i t a v e l E t e e f 0 0 6 6 e v o b a d e t a r e D s e h c n i n i s n o i s n e m i D 4 1 X 5 2...

Page 6: ...that the PV 15208 enclosure door be padlocked during normal operation Fault Reporting Any fault conditions are reported to the operator interface If the PV 15208 is equipped with LED s the red LED wil...

Page 7: ...maining load resulting in an over under frequency or voltage condition The PV 15208 then performs an orderly shutdown The fault condition will remain until the utility voltage and frequency have retur...

Page 8: ...utility it is not necessary to connect the neutral X0 to ground The PV 15208 is a balanced three phase current sourcing inverter and only operates with the presence of a stable utility voltage Single...

Page 9: ...ing fan operation 2 Maintain a minimum 1 clearance to the left and right of the PV 15208 Installation 1 The unit must be mounted at least 3 off the ground and 12 above any horizontal surface 2 Screw t...

Page 10: ...to a PV cabinet ground stud If ground fault detection is required route this jumper through CT1 located on the lower right hand corner of the control board see the system schematic for further detail...

Page 11: ...and configures the modulator drivers accordingly 3 Phase 208 VAC inverter output main contactor see picture to terminals of the 208 VAC delta side of isolation transformer If the inverter side of the...

Page 12: ...nual Copyright 2000 Xantrex Technologies Inc Trace Technologies Corp DOCUMENT 150919 3 5 Wiring Diagram Frame Ground Line Circuit Breaker Isolation Transformer PV 15208 Inverter To Single Point Electr...

Page 13: ...URE The following procedures are intended to verify correct installation and proper operation of the PV 15208 These steps are to be followed sequentially Do not continue if any of the steps or results...

Page 14: ...system faults Once all faults are cleared the amber indicator light will come on indicating the PV 15208 is in standby Close all PV array string disconnect switches if present Close the main PV discon...

Page 15: ...to the utility grid the PV 15208 will wait 5 minutes before starting to insure the voltage is not transient in nature This keeps the system from cycling during unstable irradiance conditions Power Tr...

Page 16: ...en LED will flash a sequence indicating the fault code See section 5 Troubleshooting The on off switch is used to enable or disable system operation The on off switch is also used to reset the inverte...

Page 17: ...le and efficient operation of the PV 15208 connected with any PV array configured for a 330 500 VDC peak power voltage point Below is a list of the PV 15208 operating parameters showing valid ranges a...

Page 18: ...6 n i M _ q e r F e l b a w o l l A m u m i n i M y c n e u q e r F y t i l i t U 0 3 6 0 7 5 z H 1 0 5 9 5 y a l e D _ x a M _ q e r F e l b a w o l l A m u m i x a M A o T e s n o p s e R e m i T y...

Page 19: ...problem cannot be corrected contact your Xantrex Trace Technologies distributor for assis tance or service FAULT CONDITIONS AND TROUBLESHOOTING Fault Code Annunciation The PV 15208 will report faults...

Page 20: ...e u q e r F r e v O e n i L C A 6 0 0 8 0 x 0 w o L e g a t l o V e n i L C A 7 0 0 1 0 x 0 h g i H e g a t l o V e n i L C A 8 0 0 2 0 x 0 e g a t l o V r e v O s u B C D 9 0 2 0 0 x 0 t l u a F m e...

Page 21: ...grounded in more than one location If the PV array is grounded through CT1 it must not be grounded at any other location CT1 defective Contact your Xantrex Trace Technologies distributor for assistanc...

Page 22: ...auses The utility voltage fell below the allowable limit 195 5 VAC by default Verify the utility voltage is stable and within allowable operating limits There is a problem with one or more of the AC s...

Page 23: ...blem with the integrated bus board or DSP control board Emergency Stop Fault The on off switch located on the front door of the enclosure is disabled The contact block on the back of the switch must b...

Page 24: ...eal If damaged replace with equivalent closed cell foam gasket Call your Xantrex Trace Technologies distributor for factory replacements or specifications Electrical Connections Inspect the condition...

Page 25: ...move any lockout devices from the isolation transformer circuit breaker and PV disconnect switch 2 Close the isolation transformer circuit breaker 3 Close the AC disconnect if present 4 Close the PV a...

Page 26: ...ter PV Series 150921 Rev B Assembly Main Enclosure Control Components 15 KVA PV 15208 Table of Components 150920 Rev B Envelope Drawing Grid Tied Inverter PV 15208 Underwriters Laboratories Listing Do...

Page 27: ......

Page 28: ......

Page 29: ...15 25 3 1 1 151146 01 Fab Fan Shroud 4 1 T1 1 150438 01 Transformer 80VA 5 1 T2 1 150446 01 Transformer 40VA 6 1 K1 1 150668 65 Contactor 3P 24VDC Coil 65A 7 1 TB1 2 1 150410 01 Block Power Distribut...

Page 30: ......

Page 31: ......

Page 32: ......

Page 33: ......

Page 34: ......

Page 35: ...ANGE OUTPUT WIRE RANGE CB 10H20 3R 14 to 8 6 to 2 CB 10HD8 3R 14 to 8 6 to 2 CB 12H20 3R 14 to 6 2 14 to 2 1 0 CB 12H20 4 14 to 6 2 14 to 2 1 0 For Model numbers CB 10H20 3R and CB 10HD8 3R reference...

Page 36: ...Copyright Trace Technologies Document D07200 Rev B Sept 27 2000...

Page 37: ......

Page 38: ......

Reviews: