Test Procedures
NOTE: Refer to the inverter’s operator’s manual for
setting the RY11 relay for testing.
Immediately after installation, the ALM should be tested for proper operation.
• Ensure the AUX RELAY switch on the ALM is in the ON (ENABLED) position
and the INVERTER ERROR relay is in the RELAY READY position.
• Reconnect all power to the inverter.
• Using the inverter’s control device (i.e., display, SWRC remote), press the
INV MENU button to access the inverter menu. Select ON from the display.
The blue INVERTER OPERATIONAL LED should immediately turn ON.
NOTE: The LEDs will turn ON differently, depending
upon the function selected from your inverter.
• If an external alarm is connected to the ALM, turn the INVERTER ERROR
switch to the RELAY TEST position. The external device should activate.
• Place the INVERTER ERROR switch in the RELAY READY position.
NOTE: If the tests did not pass, recheck the wiring and
the ALM for proper relay contact selection (N.O. or N.C.).
3.0 OPERATION
Summary of Contents for ALM - REV A
Page 1: ...Owner s Manual Auxiliary Load Module...
Page 10: ...1 0 INTRODUCTION 2001 Xantrex Technology Inc P N 975 0027 01 01 Rev A 09 01 6 Notes...
Page 18: ...2 0 INSTALLATION 2001 Xantrex Technology Inc P N 975 0027 01 01 Rev A 09 01 14 Notes...
Page 26: ...2001 Xantrex Technology Inc P N 975 0027 01 01 Rev A 09 01 22 3 0 OPERATION Notes...
Page 28: ...4 0 TROUBLESHOOTING 2001 Xantrex Technology Inc P N 975 0027 01 01 Rev A 09 01 24 Notes...
Page 30: ...5 0 SERVICE INFORMATION 2001 Xantrex Technology Inc P N 975 0027 01 01 Rev A 09 01 26 Notes...
Page 32: ...6 0 WARRANTY 28 2001 Xantrex Technology Inc P N 975 0027 01 01 Rev A 09 01 Notes...
Page 34: ...7 0 SPECIFICATIONS 2001 Xantrex Technology Inc P N 975 0027 01 01 Rev A 09 01 30 Notes...
Page 35: ......