SERVICE AND SPARES
Greenstar i System Compact - 6 720 807 726 (2013/05)
51
Fig. 114 Access to the cables
[1]
Low voltage cable inlet
[2]
Mains voltage cable inlet
[3]
HCM - Heating Control Module
[4]
Pressure gauge
[5]
Low voltage connectors
[6]
Mains voltage and earth connectors
REMOVING THE CONTROL UNIT
▶ Support the control unit and detach the control unit support strap.
1. Remove the hinge locking pieces.
2. Release the two catches underneath the panel.
3. Hinge the control unit up to approximately 45°.
4. Push inwards and upwards to disengage the control unit from the
hinge supports.
▶ Remove the support strap from the control unit.
▶ Fit the new control unit in the reverse order.
▶ Attach support strap to the new control unit.
▶ Reconnect all the cables previously disconnected under the access
cover.
▶ Replace the access cover and secure with the screw.
▶ Reconnect the cables previously disconnected under the installer
access cover.
▶ Replace the installer access cover and secure with the three screws
removed earlier.
Fig. 115 Removing the controller
6.8.25 EXPANSION VESSEL
The expansion vessel can be replaced with the boiler in place if there is a
side exit flue fitted and a minimum clearance of 450mm above the boiler
casing.
If a vertical flue is fitted then a similar clearance to one side of the flue is
required.
If the clearance is not available, then the boiler will need to be removed
from the mounting frame to gain access to the expansion vessel.
Alternatively a second vessel of at least the capacity of seven litres can
be fitted to the return pipe from the heating system as close as possible
to the boiler.
EXPANSION VESSEL REPLACEMENT (BOILER IN PLACE)
▶ Isolate the power from the boiler.
▶ Lower the control panel into the service position.
▶ Isolate the boiler from the heating system using the service valves.
▶ Drain the boiler.
▶ At the pump manifold, release the clip and disconnect the expansion
vessel.
▶ Pull the vessel up and out over the flue system or to one side if a
vertical flue is fitted.
▶ Fit a new “O” ring (supplied in the spares kit) to the replacement
vessel
▶ Reassemble the expansion vessel into the wall frame and slide down
the runners until the end pipe is reconnected into the pump manifold.
▶ Secure the pipe with spring clip.
CAUTION:
Earth cables must be reconnected.
1.
6720646608-72.1W
o
2.
3
2
1
4
5
6
4.
3.
6720646609-43.1W
o
2.
2.
1.
1.