UNPACKING THE BOILER
INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER GREENSTAR CAMRAY KITCHEN 12/18-18/25-25/32
8 716 113 000a (01/07)
18
IN
ST
AL
LA
TI
O
N
Unpacking:
It is advised that at least two or more persons are
involved in the transfer of the packaged boiler from
the van to the point of delivery.
1
4
Once the packaged boiler has been
delivered, the outer carton is removed first.
Care should be taken when releasing the
straps. If a sharp implement is used make
sure the outer carton is not pierced and that
the implement is used in such a way so that it
may not cause personal injury. All sharp
objects must be covered or the blade
retracted after use and put away in a safe
place.
2
4
Lift carton up and away from the boiler.
4
Remove the plastic bag and upper front
protection cover from the boiler and place
safely aside.
4
At least two or more persons are required
to move the boiler taking care not to damage
the boiler, panels or the floor.
At all times the correct method for handling
heavy objects should be strictly observed.
UNPACKING THE BOILER
LIFTING AND CARRYING PRECAUTIONS:
• Lift only a manageable weight, or ask for
help.
• When lifting or putting things down, bend
the knees, and keep the back straight
and feet apart.
• Do not lift and twist at the same time.
• Lift and carry objects close to the body.
• Wear protective clothing and gloves to
protect from any sharp edges.
I
IMPORTANT: All the previous Pre-Installation sections must be read
and requirements met before starting boiler or flue installation.
1
2
Summary of Contents for 12/18
Page 53: ...52 ...
Page 54: ...53 ...
Page 76: ...NOTES GREENSTAR CAMRAY KITCHEN 12 18 18 25 25 32 8 716 113 001a 01 07 17 NOTES NOTES ...