8. Commissioning
Gearless Lift Machine
WSG-W8
Operating Instructions
The following points should be checked or completed:
•
Remove all securing, auxiliary and installation tools
from the danger area.
•
Check that the lift machine is used for its intended
purpose and that the permissible ambient conditions
are met.
•
Check that the lift machine is properly fastened.
•
Are all bolts tightened with the specified torque and
secured?
•
Check the motor connection, especially the earthing.
•
Check that the temperature monitoring devices are
properly connected and functioning.
•
Check that the brakes are properly connected and that
the brake monitoring switches are functioning properly.
•
Is the measuring system properly connected?
•
Check that the offset value indicated on the measuring
system agrees with the value set on the converter.
•
Check the proper functioning of the brake; perform a
braking test using one (or two with the WSG-W8.4)
partial brake(s).
•
Is the rope slip-off guard properly tightened and adju-
sted?
•
Check the remote control of the brake using the Bow-
den cable, if provided.
An initial functions test of the motor and
the brake, together with the converter,
should be performed before the ropes are
put in place.