Assembly and tests 

The  test  shall  be  made  while  the  car  is 
descending,  with  1.1  times  the  rated  load 
uniformly  distributed  over  the  car  area, 
keeping  the  downward  valve(s)  open  at  the 
rated speed until the ropes become slack. 
 
Before starting the test, for your own interest, 
a working space in accord to the process must 
be  facilitated  and  any  action  must  be  done 
after considering first the consequences. 
 
The  safety  gear  test  device  is  supplied  as 
described in the next figure. 
 
The steps to follow to carry out the test are: 
 

A.

  Predispose  the  drive  rope  (3),  out  of  the 

lifting  platform  enclosure,  (closest  landing 
floor). 

 

 
 

B.

 Remove the safety clevis (2) from the device. 

 

C.

  Out  of  the  enclosure,  pull  the  rope  (3),  in 

the 

indicated 

direction 

provoking 

the 

disengagement of the device. 
 

D.

  The  disengaging  of 

the  safety  gear  will  be 

carried 

out  manually,  placing  again  the  safety 

clevis. 
 
This operation will be carried out from the pit 
safely because the lifting platform is engaged. 
 
Check  that  the  marks  caused  by  the  rollers  in 
the  guides  are  similar.  If  one  of  the  stamps 
predominates  on  the  other,  check  the 
regulation  applicable  to  safety  gear  system  in 
point  2  of  the  Safety  Gear  Guide 
1117.32.0017V01. 
  
The disengagement of the lifting platform will 
be  carried  out  by  means  of  using  the  pump 
located  in  the  hydraulic  central,  in  upwards 
direction and carried out by trained personnel. 
 
After  safety  gear  test,  the  safety  gear  test 
device  must  be  installed  again  in  its  original 
position. 
 

Rope slackening contact 

 

Verify  that  the  contact  operates  when  rope 
become  loose.  Once  the  safety  gear  test  was 
done,  the  tension  on  the  controller  terminal 
box X05 and common have to be between 100 
and  120  volts  and  the  measure  between  the 
common terminal and X07 have to be 0 volts. 
If  these  values  are  not  recorded  then  it  is 
possible that loosening of the contact is poorly 
installed or undocked. Adjust it and repeat the

 

measurement.

  

 

Summary of Contents for HHL-W Line

Page 1: ...Home Lift Elevating platform Test instructions Subject to change without notice EXCELLENCE IN COMPONENTS Date 07 10 2011 Sheet 1 Version 11117320015V02 Approved ISC Original instructions...

Page 2: ...urpose and scope of application of these instructions 2 Designations and terms 3 Safety advice 4 Description 4 1 Planning and measuring equipment 4 2 Failures Evaluation 4 3 Test methods 4 3 1 General...

Page 3: ...for braking and holding the car if it is travelling with over speed or if the suspension ropes break Pit The part of the well below the lowest stop that the car stops at Drive Equipment that moves and...

Page 4: ...lease also be safety conscious and aware of potential hazards The assembly company or service company should eliminate malfunctions that could impair safety Hazard from damaged components The lifting...

Page 5: ...ation shall be Negative N when the failure represents a serious risk for the user s safety In the relative report see Annexes 1 and 2 to the N qualified points there must be the failures to repair or...

Page 6: ...Both machine room door and machinery cabinet door must open on the outer direction Ventilation The machine rooms and cabinets must have enough ventilation outlets In case of machinery cabinets these...

Page 7: ...peed for not exceed 0 15 m s timing the platform travel from the lowest to the higher position and vice versa so that it does not exceed the amount t sec t sec travel m 0 15 m sec Unscrew the screw n...

Page 8: ...occur 4 3 4 Controller Cabinet fixing Check that the controller cabinet has the suitable fixings to the machine room walls or the machinery cabinet General connections Check that the connections on th...

Page 9: ...case of power supply failure Alarm Check the correct acting of the alarm button and the telephone system According the EN81 41 check that the phone line is in perfect condition and that the outgoing...

Page 10: ...ater Hinged support This item will only be necessary for verification when the systems if fitted with a hinged support for ensuring the security space in the pit Check the rigidity of the hinged suppo...

Page 11: ...he device D The disengaging of the safety gear will be carried out manually placing again the safety clevis This operation will be carried out from the pit safely because the lifting platform is engag...

Page 12: ...inal examinations and tests before putting into use the platform The Installation Company is the responsible of doing this final test or contracting a Notified Body to do it according to this procedur...

Page 13: ...f the examiner examination certificate examination N 1 Category type and make or trade name 2 Manufacturer s name and address 3 Name and address of certificate holder 4 Date of submission for examinat...

Page 14: ...instructions Subject to change without notice EXCELLENCE IN COMPONENTS Date 07 10 2011 Sheet 14 Version 11117320015V02 Approved ISC Original instructions Annex 2 Check list form sample Take the follo...

Reviews: