Home Lift - Elevating platform 

 

Test instructions 

 

 Subject to change without notice!

 

EXCELLENCE IN COMPONENTS

 

Date 

 

07/10/2011 

Sheet 

 

10 

Version 

 

11117320015V02 

Approved   

ISC

 

 

Original instructions 

 

Door fixing 

Check the door fixings at each stop. 
 

Earth connection at door lockings 

Check  that  the  earth  connections  that  joint 
door frames, door lockings and contacts are in 
perfect  state  and  connected  to  guides  and  to 
the general earth. 
 

Rope wedge sockets 

Check the state of wedge sockets in car. 

 
Sliding shoes 

Check  the  state  of  the  car  sliding  shoes, 
controlling also that there is no space between 
them and the guides. 
 

Additional installations 

The well shall be exclusively used for the lifting 
platform. It shall not contain cables or devices, 
etc.,  other  than  for  the  lifting  platform.  The 
well may, however, contain heating equipment 
for  the  lifting  platform  well  excluding  steam 
heating  and  high-pressure  water  heating. 
However,  any  control  and  adjustment  devices 
of  the  heating  apparatus  shall  be  located 
outside the well. 
 

Top clearances 

Please  check  that,  once  the  ram  is  in  its 
ultimate  position,  the  free  vertical  distance 
between  the  level  of  the  highest  area  on  the 
car roof and the level of the lowest part of the 
ceiling of the web is at least 300 mm. 
 

4.3.8

 

Pit 

The lower part of the well shall consist of a pit, 
the  bottom  of  which  shall  be  smooth  and 
approximately level, except for guide rail bases 
and water drainage devices. 
 
After the building-in of guide rail fixings, etc., 
the  pit  shall  be  impervious  to  infiltration  of 
water. 
 

Hinged support

 

This item will only be necessary for verification 
when  the  systems  if  fitted  with  a  hinged 

support  for  ensuring  the  security  space  in  the 
pit.  Check  the  rigidity  of  the  hinged  support. 
Load  the  platform  with  1.1  times  of  the  rated 
load,  position  at  the  first  stop  nearly  the 
lowest stop and place the hinged support in its 
active position (vertical position). DO NOT STAY 
IN  THE  PIT  AT  THIS  TEST.  Then  lower  the 
platform by using the manual valve located in 
the  valve  group  of  Hydraulic  Drive  Minilift  at 
rated  speed  until  impact  with  the  support

Check  the  integrity  of  the  support  and 
platform.

 

 

4.3.9

 

Safety gear device 

 
The energy, which the safety gear is capable of 
absorbing  at  the  moment  of  engagement,  will 
have been verified in the type tests. The aim of 
the test before putting into service is to check 
the  correct  mounting,  correct  setting  and  the 
soundness 

of 

the 

complete 

assembly, 

comprising  car,  safety  gear,  guide  rails  and 
their fixing to the building. 
 

Liabilities and guarantees 

This  instructions  booklet  is  focused  on  people 
familiarized with assembly and maintenance of 
lifting  platforms.    Enough  knowledge  is 
required in this field. 
 
WITTUR does not accept liabilities for damages 
caused  by  inappropriate  use  or  actions 
contrary  to  this  instructions  booklet  or  for 
applications out of the established using range. 
 
The  guarantee  is  declared  null  if  any 
component is used in other way than described 
in this instructions booklet. 
 

Preventive safety measures 

Staff  whom  assembly  or  maintain  Wittur 
components  are  always  responsible  for  their 
own safety. 
 
The  Staff  has  to  observe  all  the  measures  and 
legal requirements needed to avoid physical or 
personal  damages  during  the  setup  and 
maintenance. 

Summary of Contents for HHL-W Line

Page 1: ...Home Lift Elevating platform Test instructions Subject to change without notice EXCELLENCE IN COMPONENTS Date 07 10 2011 Sheet 1 Version 11117320015V02 Approved ISC Original instructions...

Page 2: ...urpose and scope of application of these instructions 2 Designations and terms 3 Safety advice 4 Description 4 1 Planning and measuring equipment 4 2 Failures Evaluation 4 3 Test methods 4 3 1 General...

Page 3: ...for braking and holding the car if it is travelling with over speed or if the suspension ropes break Pit The part of the well below the lowest stop that the car stops at Drive Equipment that moves and...

Page 4: ...lease also be safety conscious and aware of potential hazards The assembly company or service company should eliminate malfunctions that could impair safety Hazard from damaged components The lifting...

Page 5: ...ation shall be Negative N when the failure represents a serious risk for the user s safety In the relative report see Annexes 1 and 2 to the N qualified points there must be the failures to repair or...

Page 6: ...Both machine room door and machinery cabinet door must open on the outer direction Ventilation The machine rooms and cabinets must have enough ventilation outlets In case of machinery cabinets these...

Page 7: ...peed for not exceed 0 15 m s timing the platform travel from the lowest to the higher position and vice versa so that it does not exceed the amount t sec t sec travel m 0 15 m sec Unscrew the screw n...

Page 8: ...occur 4 3 4 Controller Cabinet fixing Check that the controller cabinet has the suitable fixings to the machine room walls or the machinery cabinet General connections Check that the connections on th...

Page 9: ...case of power supply failure Alarm Check the correct acting of the alarm button and the telephone system According the EN81 41 check that the phone line is in perfect condition and that the outgoing...

Page 10: ...ater Hinged support This item will only be necessary for verification when the systems if fitted with a hinged support for ensuring the security space in the pit Check the rigidity of the hinged suppo...

Page 11: ...he device D The disengaging of the safety gear will be carried out manually placing again the safety clevis This operation will be carried out from the pit safely because the lifting platform is engag...

Page 12: ...inal examinations and tests before putting into use the platform The Installation Company is the responsible of doing this final test or contracting a Notified Body to do it according to this procedur...

Page 13: ...f the examiner examination certificate examination N 1 Category type and make or trade name 2 Manufacturer s name and address 3 Name and address of certificate holder 4 Date of submission for examinat...

Page 14: ...instructions Subject to change without notice EXCELLENCE IN COMPONENTS Date 07 10 2011 Sheet 14 Version 11117320015V02 Approved ISC Original instructions Annex 2 Check list form sample Take the follo...

Reviews: