O p e r a t i n g I n s t r u c t i o n s
OKTOPUS
®
GLASS-Jack
GL-RN 400/600/800
Technical Documentation
BA 000 101
Annex 1
Abridged operating instruction
OKTOPUS
®
GLASS-Jack GL-RN 400/600/800
1 Assembly
(1) Configurate the OKTOPUS
®
in correspondence with the application, and fix to the crane
hook.
2 Start-up of the OKTOPUS
®
(1) Place the OKTOPUS
®
onto the element to be sucked.
(2) Turn the main switch to ON position.
(3) Slightly lift the switch „Suction/Release“ and push towards „Suction“.
(4) Check the charging status of the battery via charge indicator.
•
the green LED shows readiness for operation,
•
when the third LED from the left (yellow LED) lights up, the battery should be charged,
•
when the second LED from the left (yellow LED) flashes or the second LED from the left
(yellow LED) and the red LED light up in turns, the battery must be charged.
(5) Check vacuum pressure at the vacuum gauge (permissible green sector -0.65 to -0.9 bar):
•
In case pressure in one or in both gauges is in the red sector, the alarm will be activated
and vacuum needs to be built up.
•
If pressure in both vacuum gauges is in the green area, the OKTOPUS
®
is ready for op-
eration; the red signal light switches off and the green signal lamp turns on.
3 Instruction for use
(1) Preparation of the elements:
•
Check the surface of the element: The surface shall be smooth, airtight, clean and dry
at least at the suction spots. There must not be any protection film in the suction area.
(2) Lifting the element:
•
Place the OKTOPUS
®
onto the element.
•
Slightly lift the switch „Suction/Release“ and push towards „Suction“.
(3) Positioning the element:
•
Erect/lift the element by crane lifting movement,
•
Positioning of the element by crane driving and lifting movement together with simulta-
neous manual guidance of the element by the installer.
•
Fixation of the element to the installation point.
(4) Detaching the element
•
Slightly lift the switch „Suction/Release“ and push towards „Release“.
4 Shutdown
•
Lower the crane.
•
Separate the connection OKTOPUS
®
/ crane.
•
Turn the main switch of the OKTOPUS
®
to OFF position.
•
In case of shutdown over a longer period, the batteries of the OKTOPUS
®
shall be
charged at least every 2 weeks.