Commissioning
en
Installation and operating instructions Wilo-Padus PRO
19
ƒ
Making the installation and operating instructions available in the language of the
personnel.
ƒ
Making sure that the installation and operating instructions are read and understood
by all personnel.
ƒ
All safety devices and emergency cut-outs on the system-side must be active and
checked to ensure that they work properly.
ƒ
The pump is suitable for use under the specified operating conditions.
7.3
Direction of rotation check (for
three-phase current motors only)
The pump has been checked and adjusted to the correct direction of rotation for a
clockwise rotating field at the factory. Connection is made in accordance with the spe-
cifications in the “Electrical connection” chapter.
Checking the direction of rotation
A qualified electrician checks the rotating field at the mains connection with a rotating-
field testing device. To allow the correct direction of rotation, a clockwise rotating field
must be available at the mains connection. The pump is
not
approved for operation
with a counter-clockwise rotating field!
CAUTION! If the direction of rotation is
checked with a test run, comply with the environmental and operating conditions!
Incorrect direction of rotation
If the direction of rotation is incorrect, exchange the two phases at the mains connec-
tion.
Pumps with CEE plug and phase inverter
AUTO
RESET
180°
ON
OFF
1
2
Fig. 6: Phase inverter
1. Insert CEE plug into the socket.
2. Check the control lamp.
⇒ Control lamp off: Direction of rotation correct.
⇒ Control lamp on: Incorrect direction of rotation.
3. Correct the direction of rotation.
⇒ Use a suitable screwdriver to push the phase inverter into the plug and turn by
180°.
▶ Direction of rotation set correctly.
7.4
Operation in an explosive atmo-
sphere
Operation in an explosive atmosphere is not permitted.
7.5
Before switching on
Check the following prior to activation:
ƒ
Check whether the device has been installed properly and in accordance with the
locally applicable regulations:
–
Has the pump been earthed?
–
Has the power supply cable routing been tested?
–
Has the electrical connection been carried out in accordance with regulations?
–
Are all mechanical components attached correctly?
ƒ
Check level control:
–
Can the float switches move freely?
–
Have the switching levels been tested (pump on, pump off, minimum water
level)?
–
Is additional dry-running protection installed?
ƒ
Check the operating conditions:
–
Have the min./max. temperatures of the fluid been tested?
–
Has the max. immersion depth been checked?
–
Is the max. switching frequency complied with?
–
Has a hard base been installed in the case of soft flooring?
–
Are all gate valves open?