CAUTION
Material damage due to incorrect fixation
Defective fixation may limit the functionality of the mixer or damage it.
• If the mixer is fixed to a concrete structure, use anchor bolts for fixation. Follow the
manufacturer’s installation instructions! Temperature specifications and hardening
periods must be strictly observed.
• If the mixer is fixed to a steel structure, ensure that the structure is sufficiently
strong. Use fixation materials with sufficient strength!
Use suitable materials to avoid electrochemical corrosion!
• Tighten all screwed connections. Observe torque specifications.
ƒ
Wear protective equipment! Observe the work regulations.
–
Protective gloves: 4X42C (uvex C500)
–
Safety shoes: Protection class S1 (uvex 1 sport S1)
–
Wear a safety harness.
–
Safety helmet: EN 397 Conforms to standards, protection against lateral deform-
ation (uvex pheos)
(When using lifting equipment)
ƒ
Prepare the installation site:
–
Clean, free of coarse solids
–
Dry
–
Frost-free
–
Disinfected
ƒ
Work must always be carried out by two persons.
ƒ
Demarcate the working area.
ƒ
Keep unauthorised persons away from the working area.
ƒ
From a working height of more than 1 m (3 ft) above the ground, use scaffolding
with a safety harness.
ƒ
Toxic or asphyxiating gases may build up during work:
–
Observe protective measures in accordance with work regulations (gas measure-
ment, carry a gas detector with you).
–
Ensure adequate ventilation.
–
If toxic or asphyxiating gases accumulate, leave the workplace immediately!
ƒ
Install lifting equipment: even surface, clean, firm base. Warehouse and installation
location must be easily accessible.
ƒ
Attach chain or wire rope to handle/attachment point with a shackle. Only use lifting
gear that has been technically approved.
ƒ
Do not stay within the swivel range of the hoisting gear.
ƒ
All connection cables must be laid properly. The connection cables must not pose
any risk (i.e. tripping, damage during operation). Check whether the cable cross-sec-
tion and the cable length are sufficient for the selected installation type.
ƒ
Observe minimum clearances to walls and any fixtures.
6.4.1
Maintenance tasks
After a storage period of more than 12 months, carry out the following maintenance
tasks before installation:
ƒ
Rotate propeller.
See section “Rotating the propeller [
}
71]”.
ƒ
Seal housing oil change.
See section “Oil change [
}
73]”.