7.2 

Volumetric method 

Only possible if no extra gas is pumped into the net by the GVU. 
Wobbe-Index W

and net heating value H

uB

 to be requested from the gas supply company. 

1.  Take  off  cover  plate  (15),  pressure  adjusting  screw  at  measure  nozzle  (30)  and  connect  U-tube-manometer.  Open  gas 

stop cock and put appliance into operation (see page 7). 

2.  Read  existing  connection  flow  pressure  at  U-tube-manometer.  For  natural  gas,  the  connection  flow  pressure  should  be 

between 18 mbar and 25 mbar. 

3.  Should the connection flow pressure vary from the above mentioned values, the cause needs to be established and the 

fault to be rectified. Should this not be possible, the gas supplier needs to be contacted.  

4.  Open gas stop cock and put appliance into operation according to „Commissioning“ (page 7). 
5.  Check  that  the  water  temperature  in  the  tank  is  not  higher  than  lukewarm  to  50°C,  cool  by  emptying  some  water  if 

necessary.  Turn temperature regulation button (20) to position “6”. 

6.  Adjust  the  die  pressure  that  is  stipulated  in  the  table  on  page  10  by  turning  the  pressure  adjusting  screw  (17)  of  the 

pressure regulator (14). The die pressure is increased by turning to the right and decreased by turning to the left. 

7.  Turn the temperature control button (20)   to OFF position and close gas stop cock 
8.  Safety check: Close gas stop cock for 20 – 45 seconds. The safety pilot should audibly close after the gas stop cock has 

been closed.  

9.  Switch  the  temperature  control  (20)  button  to  OFF    (24).  Take  off  the  U-tube-manometer  only  when  gas  stop  cock  is 

closed. Screw in screw of the measure nozzle (30) gas tight.  

10.  Replace cover plate (15). 

8  Conversion to other gas types 

Any conversion is only to be undertaken by a registered specialist. 

8.1 

From natural gas to liquid gas 

8.1.1. 

Close gas stop cock and remove cover plate (15).

 

8.1.2. 

Remove burner unit: Loosen screws for the gas supply line (32), ignition gas line (33) and thermal power line (31) at 
the  regulator.  Lift  the  burner  unit  from  the  2  centre  bolts  at  the  support  and  move  everything  slightly  forward.  Now 
place on bottom tray and remove.

 

8.1.3. 

 Exchange main nozzle (40). For nozzle diameter see table on page 10. 

8.1.4. 

Loosen screws (41) of the ignition gas line (33) at the pilot burner (13) and exchange nozzle. The nozzle number can 
be found in the table on page 10. Re-attach the ignition gas line (33) gastight by using the screws (41). 

 

8.1.5. 

 

Relocate burner unit on centre bolts. Screw back gas supply line (32) and ignition gas line (33) onto the regulator and 

make sure that it is gastight. Screw back the thermal power line (31) hand tight.  

8.1.6 

Remove  cover  cap  (25).  Remove  pressure  regulator  (14)  and  replace  with  maximum  set  screw  No.  228.  The  die 
pressure is about equal the connection pressure. 

8.1.7. 

 Open gas stop cock and check pipes and gas fittings on tightness. Replace cover cap (25) and fix screws. 

8.1.8 

Close gas stop cock 

8.1.9.   Place new sticker „Type of gas“ on the gas fittings. 
8.1.10    Replace cover plate (15). 

8.2 

From liquid gas to natural gas 

8.2.1.   Follow points 8.1.1 till 8.1.5 
8.2.2.   Remove cover cap (25). Remove maximum set screw No. 228 and 
               install pressure regulator (14). Set nominal load according to “Gas                 
               regulation“ (page 8). 

8.2.3.   Follow points 8.1.7. till 8.1.10 

8.3 

From natural gas group E to natural gas group LL or vice versa 

8.3.1      Close gas stop cock and remove cover plate (15). 
8.3.2. 

Remove  cover  cap  (25).  Set  nominal  load  according  to  “Gas    
regulation“ (page 8). Replace cover cap (25) and fix screws.  

8.3.3       Place new sticker „Type of gas“ on the gas fittings. 
8.3.4       Replace cover plate (15) and open gas cock.

 

 

 

 

 

 

Summary of Contents for GS 117 E

Page 1: ...ber who observes the local norms and regulations The installation and maintenance record must be entirely completed and the user has to be instructed accordingly Efficient operation can only be guaran...

Page 2: ...uit The tank is protected against corrosion by double coated enamel and magnesium anode An insulation layer between the internal tank and the steel plate housing minimizes loss of heat The steel plate...

Page 3: ...DN 15 b Drain pipe c Water stop valve d Manometer connection nozzle e Backflow preventer f Pressure reducing valve if more than 8 bar connection pressure g Water stop valve h Test valve i Gas stop va...

Page 4: ...min 160 205 266 Gas consumption Natural gas group E HuB 9 4 kWh m3 m3 h 0 85 0 97 1 09 Natural gas group LL HuB 8 5 kWh m3 m3 h 0 94 1 07 1 20 Liquid gas propane HuB 12 8 kWh kg kg h 0 63 0 71 0 8 No...

Page 5: ...circulation pipe must be fitted at the tank only with an original connection attachment available as spare parts at the connection point Connect the circulation pump and reverse flow stopcock between...

Page 6: ...d cuts off the gas supply automatically After a period of 5 minutes switch the gas boiler can be put again into operation see commissioning No 6ff Should the appliance cut off several times via the fl...

Page 7: ...in the tank The appliance is working automatically The gas control fittings will switch off or on the main burner depending on the water temperature At the moment the appliance is switched on again th...

Page 8: ...he measure nozzle 30 gas tight 6 Remove screw of the measure nozzle 21 and connect U tube manometer 7 Open gas stop cock and put appliance into operation according to Commissioning page 7 8 Check that...

Page 9: ...ypes Any conversion is only to be undertaken by a registered specialist 8 1 From natural gas to liquid gas 8 1 1 Close gas stop cock and remove cover plate 15 8 1 2 Remove burner unit Loosen screws fo...

Page 10: ...l min at nominal load Gas volume l min at nominal load kWh m Natural gas group LL 8 5 15 5 17 6 19 8 Natural gas group E 9 4 14 1 16 1 18 0 Liquid gas propane 27 7 4 8 5 4 6 1 Net heating value HUB at...

Page 11: ...ormed of the importance of regular maintenance and that this is a decisive factor as to how long the appliance will last Openings necessary to allow air circulation around the site of installation mus...

Page 12: ...ked I Check gas supply adjust dimensions of gas pipes clean connecting pipes clean dirt filter Ignition nozzle blocked I Clean ignition nozzle The installed ignition nozzle is too small I Install corr...

Page 13: ...e has been modified through the installation of externally supplied parts or through irregular professional maintenance Subject to our general terms and conditions Legal warranty 2 years Guarantee yea...

Page 14: ...aller Signature Signature Place of installation Name ZIP Code Place Street Phone Tank model Serial number Date of invoice Anode maintenance record Date Visual examination of anode Exchange of anode Si...

Reviews: