17
11
Commissioning / Setting
11.1
Filling the Reservoir
The Electro 15 lubricators have been designed with a direct fill reservoir via a secure opening lid.
This direct fill method is the quickest and most user friendly filling method.
Access the Grease Reservoir
•
Open the lid on top of the cabinet. There are two latches (padlocks may be used to secure the
lid) that need to be released and the lid can then be hinged upwards. There is a stay in the lid
that prevents the lid from closing accidently. When the lid is open you will be able to see the
grease reservoir.
Note
– ensure only approved grease or friction modifier enters the reservoir. Any non-approved
materials could severely damage the system.
Filling the Grease Reservoir
•
Grease can be poured directly from the drum or storage bag,
into the reservoir. An Electro 15 reservoir will hold 100 kg.
•
Do not over fill the reservoir.
•
Once filled close the lid by opening it slightly then release the
stay from its lock and then the lid can be closed fully. Press
firmly shut and secure using the latches. It is important that the
lid is locked correctly; if the lid is left open the grease / modifier
may biodegrade rapidly.
11.2
Wheel Sensor Heights and Operation
Procedure for height adjustment and testing operation are covered in Section 12.10.
11.3
Pump Setting
The Electro 15 Lubricators are controlled and set by a control panel
located inside the cabinet. The control panel allows the user to set
the grease output from the Blade blades with respect to the rail
traffic using the line.
The following steps explain how to set and adjust the Lubricator
once installed.
The buttons and indicator lamps have been numbered to help
explain these instructions.