Test #5 - Console Touch Switches and Indicator Test
Refer to the Service Diagnostic Tests and run the Console Switches and Indicator
Test routine.
Start the test by pressing the
Start
button.
1.
No LEDs light up
a) Visually check that connectors P3 and P4 are inserted all the way into the control board.
b) If these connections are good, remove P3 and P4 from the control board while the
power is still on. Check the DC supply voltage to the indicator and switch assembly by
measuring the voltage between P3-4 (black lead of meter) and the following points:
•
P3-10
•
P3-11
•
P3-12
•
P3-13
•
P3-14
•
P4-2
•
P4-3
A voltage of at least 3 VDC should be measured at all of these points. If not, replace the
control board.
c) If at least 3 VDC
is
measured, replace the key switch/console assembly.
2.
A group of LEDs do not light up
a) A “group” or combination of LEDs share a common connection. If this connection is open,
all of the LEDs in the group will be disabled.
b) Replace the key switch/console assembly.
3.
A single LED is OFF
a) Press the touch switch button that is associated with the LED several times.
b) If the LED does not light up, the LED has failed.
c) Replace the key switch/console assembly.
Summary of Contents for CATALYST
Page 4: ...PB NOTES ...
Page 18: ...14 NOTES ...
Page 28: ...24 NOTES ...
Page 38: ...34 NOTES ...
Page 41: ...37 NOTES ...
Page 42: ...38 NOTES ...
Page 44: ...40 CO RPO RA TIO N ...