Westinghouse PD06OD Installation Booklet Download Page 11

Packaged Air Cooled Water Chiller

Start Up

Procedure Check Points Yes No

Equipment Inspection: a. Unit damaged on arrival

b. Material received agrees with shipping

papers

Setting Unit:

Wiring:

Piping

Alignment:

(Belt Drive Units)

Before Start-up:

After start-up:

a. Vibration isolator used

b.

Spring isolator adjusted for equal height

c. If rubber in sheer isolators are used, is

unit levelled  by shimming

a. Power wiring complete

b. Control wiring complete

c.

Electric service adequate for load

d .   P o w e r   s o u r c e   v o l t a g e   c o r r e c t   f o r

motor(s)  used

e. Motor circuit has proper size fusetrons

f. System wired per diagram

g. All lead connections tight

h. Wiring complies with local codes

a. Piping complies with applicable codes

b. External piping independently supported

c. Chilled water lines insulated

a .   A l l   b e l t s   a d j u s t e d   a n d   c h e c k e d   f o r

tautness

b. All pulleys checked and adjusted for

proper pitch, tightness and alignment

a. Check compressor for proper oil level

b. Open compressor suction and discharge

service valves.

c. Open receiver liquid valve(s)

d. Open suction, oil and discharge valves

to pressure gauges (if supplied)

e. Check rotation of all fan and blower

motors

f. All motors and bearings lubricated (Belt

Drive Units)

g. Start auxiliary equipment (Pumps. fans,

etc.)

h. Is crankcase heater operating?

a. Check oil pressure. Is pressure at Mfg’s

recommendation?

b. Re-check oil level in crankcase

c. Check high pressure control

Summary of Contents for PD06OD

Page 1: ......

Page 2: ...accessible to servicing Drain connections should be provid ed at all low points to permit complete drainage of chiller and piping system The chiller water piping should be insulated to reduce heat pic...

Page 3: ...As a result the unit may cycle on low pressure con trol with the possibility of evaporator freezing Westinghouse offers two types of system con trol allowing the units to operate at the winter ambien...

Page 4: ...2 Dial Set At 55 F Fan Cycling Ambient Thermostat Adjustable FCT 1 FCT 1 Cut In 75 F cut out 72 F FCT 2 FCT 2 Cut In 55 F cut out 52 F FCT 3 FCT 3 Cut In 38 F cut out 35 F Chiller Heater Thermostat N...

Page 5: ......

Page 6: ......

Page 7: ...s Cl C3 C5 C7 respectively to energize fan contactor C9 when the high side pressure in creases to the cut in setting of FCP1 or FCP2 fan cycling pressure controll Fan Motor M2 and M3 are energized thr...

Page 8: ......

Page 9: ...tacts CIA C3A C5A C7A of contactors Cl C3 C5 C7 respectively to energize fan contactor C9 when the high side pressure in creases to the cut in setting of FCP1 or FCP2 fan cycling pressure control Fan...

Page 10: ......

Page 11: ...m g All lead connections tight h Wiring complies with local codes a Piping complies with applicable codes b External piping independently supported c Chilled water lines insulated a All belts adjusted...

Page 12: ...ssure switch checked Yes Low pressure freeze control If part winding start time delay is Temperature of air entering condenser Temperature of air leaving condenser Temperature of Chilled Water enterin...