Installation and operating instruction
Hydraulic unit WWP LS 8 ... 16-B
7 Commissioning
83306902 2/2017-05 La
63-88
7 Commissioning
7.1 Prerequisite
Commissioning must only be carried out by qualified personnel.
Only correctly carried out commissioning ensures the operational safety.
Commissioning must only be carried out once the cooling circuit has been installed
completely (see installation and operating manual of outdoor unit).
Prior to commissioning ensure that:
all assembly and installation work has been carried out correctly,
the unit and the system have been filled with media and vented,
cooling or heating demand exists,
the service valves on the outdoor unit are open.
Additional system-related tests could be necessary. Please observe the operating
guidelines for the individual components.