Connecting a manometer for gas
➌
Connect a manometer
To measure the gas pressure during commissioning.
(Test point
➌
)
Checklist for initial commissioning
❏
The heating appliance must be assembled ready for
operation.
❏
The operating instructions of the heat exchanger must
be followed.
❏
The whole plant must be wired correctly.
❏
The heating appliance and the heating system must
be sufficiently filled with heating medium.
❏
Flues must be free from obstructions.
❏
The ventilators on air heaters must work correctly.
❏
Sufficient fresh air must be available.
❏
The required test points for combustion analysis must
be available.
❏
Ensure that the heat exchanger and the flue gas
section up to the test opening are sound, so that the
test results are not corrupted by extraneous air.
❏
Liquid level controls must be set correctly.
❏
Thermostat, pressure switch and other safety devices
must be in operating position.
❏
There must be a demand for heat.
❏
Fuel lines must be purged of air.
❏
The soundness of the valve train must be tested and
documented.
❏
The gas supply pressure must be correct.
❏
Fuel cut off devices must be closed.
Note
Dependent on site requirements, further
checks may be necessary. Note the
instructions for the individual items of plant
equipment.