www.wave-2-wave.com
DOC -0001
Hardware
Installation Manual
Page 13
4.3
Cabling (Fiber and Ground)
4.3.1 Organizing the Fiber Cable
The slack fiber cable from the ROME chassis should be spooled and secured to the rear of the patch
panel. Sufficient slack should be allowed to fully extend the ROME chassis outwards for maintenance.
4.3.2 Grounding the ROME Chassis
Connect the customer facility ground to the ROME Chassis at the attachment point which is located at the lower
left corner when looking at the back of the ROME (refer to the pictures below).
Verify that the ground cables/wires are made of copper and that the facility ground cable is at least
10 AWG.
Rear Ground (Earth) Point
2-HOLE Compression Lug
Attach using M5 16mm screws