6
Step 6
Selecting Pipe Size
Next the unit will prompt the installer to select the size of the joint being fused.
Scroll UP or DOWN to highlight the correct size, then press START to select size.
Step 7
Selecting Heat Cycle
The unit will ask if a pre-heat cycle is needed for the joint. If fusion will be performed
where pipe temperatures are outside the range of 60 - 90 degrees F, please consult
Orion Fittings Technical department at (910) 865-7530 before proceeding. All other
fusions should be performed using the STANDARD cycle, which is selected by
pressing the START button.
Step 8
Verifying Welding Parameters
The screen will display “VERIFY WELDING PARAMETERS” and an audible beep
will sound to indicate the fusion unit is ready to begin welding. Verify the welding
data displayed on the screen matches the joint being fused. If the information is
incorrect, press the STOP/BACK button to return to any of the menu options to
correct the fusion parameters. Once the parameters have been verified, press
START to begin the fusion weld.
Fitting size selection screen
Fusion cycle type selection screen
Fusion cycle type selection screen