Commissioning Deep Well Pump Control
STEP 1
NOTE: System needs to be filled, pressurized, and ready for flow.
Pre-set pilots as noted:
Opening and Closing Speed
– Prior to pump start, actuate manual operator on solenoid to enable diaphragm assembly to stroke
open and closed. Observing the limit switch stem indicator, monitor rate of opening and closing speed. Adjust accordingly per applica-
tion requirements.
Note: Cycle diaphragm multiple times to confirm rate of movement and remove excess air trapped within the cover chambers (See
Figure 1 Below).
To increase the rate of opening/closing, turn the adjustment screws on the speed controls OUT, counterclockwise. In decrease the rate
of opening/closing, turn the adjustment screws on the speed controls IN, clockwise.
STEP 2
Prior to pump start, energize the solenoid to confirm connection
to power source.
STEP 3
De-energize the solenoid prior to initial pump start.
STEP 4
Energize the solenoid at pump start to close the main valve,
checking that the main valve closes.