STEP 1: REMOVE EXISTING FIREPLACE
STEP 2: MEASURE ALCOVE & HEARTH
STEP 3 : FILL VOIDS AROUND FIREBOX
STEP 4 : INSTALL FIREPLACE & SEAL
STEP 1a: Remove Fireplace
Once the main Chimney structure has
been assessed & complies to C1
outbreak of fire, remove existing
fireplace eg. brick or insert firebox.
STEP 1b: Clean out cavity
Once existing brick or insert
Fireplace has been removed,
Sweep out Chimney &
remove all debris from
Chimney cavity.
STEP 2: Check Cavity size
Check cavity sizes as above to suit firebox. In most cases
reducing or enlarging these dimensions may be required
to suit Firebox.
STEP 3: Fill Voids Around Firebox
Mark out firebox size on plinth & fill void around firebox with non
combustible material eg: rockwool insulation or Hebel panels is
recommended. Chamfer top of fill.
STEP 4: Install Firebox in Place
Slide firebox into place ensuring a tight seal is created on inside of
firebox flange against mantle face. Heat resistant sealant may
need to be used. Secure firebox in place.
This can be done by drilling & b\bolting through base under gas
burner. Drill to suit.