P 8
12
Please retain product label and instructions for future reference
Step 18a
Once the Roof is alligned and secure the
Floor can be fixed into postion.
Fix the building into place by screwing
through the panel into the floor making
sure to screw into the floor bearers.
*External panels not shown
64x50mm Screws
Step 18b
Continue to fix the building into place by
screwing through the panel into the floor
making sure to screw into the floor bearers.
*External panels not shown
Pre drill
hole
50mm
screw
Pre drill
hole
50mm
screw
Step 17c
Screw through panel into the alligned
Roof bearers as shown in the diagram.
Do not secure the building to the
Floor until the roof is fitted.
*External panels not shown
8x50mm Screws
Pre drill
hole
50mm
screw
Step 19
Place the Under Roof (
No. 12
) into position,
making sure it is flush to the Door panel
and Storage section.
Fix in place making sure to screw through
the Roof framing. Pre-drill holes first.
15x30mm Screws