SHB 28Z3 EN – Edition 2.0 * 28z3s510.fm
5-19
Hydraulic system
5.4
Regeneration – stick section
Problem
High loads on the stick can cause the stick ram to be “emptied” on the base side, which
can cause the stick to stop in vertical position.
Solution
A non-return valve is integrated in the stick segment so the rod-side oil can flow to the
base side.
Location
The regeneration valve is located in the stick segment on the lower side.
5.5
Bucket pre-tension
A nozzle is integrated in the pressure line of the bucket segment. If the bucket and the
boom (both supplied with oil by the same pump) are actuated at the same time, both move
simultaneously, and not the bucket (with its smaller mass) first, and then the boom with its
larger mass
– see
Main valve block diagram
on page 5-15.
Location:
Summary of Contents for 28Z3
Page 10: ...I 8 SHB 28Z3 EN Edition 2 0 28Z3s20IVZ fm...
Page 11: ...Operation...
Page 27: ...Specifications...
Page 46: ...2 20 SHB 28Z3 EN Edition 2 0 28z3s210 fm Specifications...
Page 47: ...Maintenance...
Page 113: ...Engine...
Page 132: ...4 20 SHB 28Z3 EN Edition 2 0 28z3s410 fm Engine...
Page 133: ...Hydraulic system...
Page 169: ...bersicht der Hydraulikpl...
Page 174: ......
Page 175: ...Electrical system...
Page 184: ...6 10 SHB 28Z3 EN Edition 2 0 28z3s610 fm Electrical system...
Page 185: ...Die Stromlaufpl ne und K Optionen...
Page 187: ......
Page 188: ......
Page 199: ...SHB 28Z3 EN Edition 2 0 28z3s612 fm 6 25 Electricalsystem...
Page 200: ...6 26 SHB 28Z3 EN Edition 2 0 28z3s612 fm Electrical system...
Page 201: ...Options...
Page 204: ...7 4 SHB 28Z3 EN Edition 2 0 28z3s710 fm Options Installation...
Page 230: ...7 30 SHB 28Z3 EN Edition 2 0 28z3s710 fm Options...
Page 231: ...PowerTilt PTS06...