3
Transportation and setting up of the machine/line
3.1 Notes on transportation
NOTE!
- Before transporting the machine/line the motor is to be switched off and the
mains connector plug must be pulled out!
- The machine/line must not be tipped!
- In order to avoid transportation damage assemble any available
transport securing devices.
- Secure the machine/line in an orderly manner on the means of transport!
- Observe the statutory requirements (StVO) for legally specified dimensions or mark the load!
A forklift with a lifting capacity in compliance with the table given below is required for the unloading of
the machine.
Before unloading the machine must be checked for any transportation damage, this is to be recorded
in the delivery certificate and reported to the Customer Service Department.
Ensure that the machine is not damaged by knocking it or setting it down too quickly in the course of
the manipulation.
Picture 3.1-1) Transport single belt press EBP 580
F1 load on the means of attachment
6650 N oder 665 kg
F2 foundation load
3400 N/m² oder 340 kg/m²
1
Foundation fixture
2
Transport pallet
3
Reception point on the forklift
WARNING AGAINST GENERAL DANGERS
A crane or forklift stacker with a lifting capacity in compliance with the table given
below is required for the unloading of the machine.
Means of attachment (rope, chain, belt) should be fixed only to the lifting points
provided!
The lifting accessories used must be adequate for dealing with the load as given
(See table above and nameplate on notice)!
The machine must be secured during transportation by belts or on a pallet bolted.