Cutting and fastening of end coverage
end
coverage
ridge profile
top wire bandage
bottom wire
bandage
screw М5х50
angle
2100
3
1
top coverage
top coverage
Figure28
12.
Align elements of ridge profile lengthwise installing screw threaded
ends outside (Fig. 27).
Figure27
Take polycarbonate
sheet halves connected
by
adhesive
tape
on
frame
Take
polycarbonate
sheet
halves connected
by adhesive tape on
frame from end. Install
polycarbonate
with
outstanding of the edge
out of end plane for 10-
20 mm. If side edge
of polycarbonate are
essentially nonparallel
to frame arcs’ edges, it
means that the frame
is not leveled before
screw tightening and
this operation should
be repeated. Following
sheets of polycarbonate
are prepared in similar
way and installed with
overlapping on previous
sheet for width of arc
profile.
Slide assembled ridge
profile from end side for
11.
For top coverage,
cut 6x2.1 m sheets
in halves per 3x2.1 m
pieces keeping right
angle of cutting line to
sheet side edge. Then
put halves together by
cutting line with aligning
the side edges and
positioning protective
layer outside. Eliminate
mismatch of edges
after cutting halves and
adding them together by
cutting of outstanding
edge. If outstanding
exceeds 5 mm, level both
edges by ruler to provide
right angle of cutting
edge to side edges.
Remove protective film
Figure26
adhesive
tape
adhesive
tape
3000
2100
from polycarbonate
without violation of
relative position of
sheet halves. Cover
polycarbonate combs
with adhesive tape and
then join the halves with
adhesive tape by cutting
edges (Fig. 26).
Cutting and fastening of end coverage
all length of greenhouse
over
polycarbonate
sheets. Install top wire
bandage (6 m) over
frame arc starting from
middle of each sheet
and tighten with bottom
bandage using angles
and screws M5x50 (Fig.
28).