10TA Service Manual
MAINTENANCE
4/15/14
7-8
Preventive Maintenance
A careful inspection of the Tube-Ice
®
machines refrigeration system
for leaks and correct operational functions at time of installation will start its long satisfactory life of
service. In order to insure this degree of dependability, a systematic maintenance program is
recommended. Therefore, the following schedule is suggested as a minimum.
A.
Daily
1.
Check operating pressures (suction, discharge, oil).
2.
Check ice quality.
3.
Check “ice out” time (maintain 30 seconds of continued harvest after last ice is out).
4.
Check compressor oil level.
5.
Check refrigerant operation level.
6.
Check frost pattern on freezer shell and oil trap.
7.
Check make-up water float valve adjustment.
B.
Weekly (in addition to daily checks)
1.
Check for leaks after 400 hours or four weeks of operation
C.
Monthly (in addition to weekly checks)
1.
Check calibration and operation of all controls (high & low press switches, oil press switch, etc.)
2.
Check cooling tower spray nozzles and pump suction screen for scaling and algae (consult
water treatment suppliers for corrective measures).
3.
Check water distributors in freezer for scale accumulation.
4.
Check water tank for solids to be removed.
5.
Check all motor drive units (compressor, cutter and pump motors, cooling tower fan, and
pump, etc) for abnormal noise and/or vibrations.
6.
Check oil level in gear reducer.
7.
Check one complete freeze/thaw cycle, record data and compare with production check of
Registration/Start-up Report.
D.
Yearly (in addition to weekly and monthly)
1.
Check entire system for leaks.
2.
Drain water from condenser and cooling tower and check condenser tubes. Check closely for
damage by corrosion or scale.
3.
Remove all rust from all equipment, clean, and paint.
4.
Check all motors for shaft wear and end play.
5.
Check operation and general condition of all electrical controls, relays, motor starters, and
solenoid valves.
6.
Check freezing time, ice release time, and ice out time.
7.
Change oil in gear reducer box once a year.
PRESSURE RELIEF VALVES MUST BE REPLACED AFTER 5 YEARS OF SERVICE.
BEFORE REPLACING RELIEF VALVE, REVIEW REQUIREMENTS PER CURRENT
LOCAL AND NATIONAL CODE.
NOTE: IF RELIEF VALVE DISCHARGES, VALVE MUST BE REPLACED BECAUSE SETTING OR SEAT
TIGHTNESS MAY BE ALTERED.
CONTACT VOGT ICE PARTS DEPARTMENT FOR REPLACEMENT VALVES.
PHONE: 502-635-3000
Summary of Contents for P18FXT
Page 4: ...Vogt Tube Ice Machines Installation Service Manual and Parts Catalog 12A4171M08 10TA Model ...
Page 10: ...10TA Service Manual TABLE OF CONTENTS vi BLANK ...
Page 20: ...10TA Service Manual INTRODUCTION 4 14 14 1 10 BLANK ...
Page 40: ...10TA Service Manual INSTALLING YOUR TUBE ICE MACHINE 4 14 14 3 18 BLANK PAGE ...
Page 50: ...10TA Service Manual START UP AND OPERATION 4 14 14 5 6 BLANK ...
Page 60: ...10TA Service Manual ELECTRICAL CONTROLS 4 14 14 6 10 BLANK ...
Page 112: ...10 8 10TA Service Manual OPTIONS AND ACCESSORIES BLANK ...
Page 120: ...10TA Service Manual TABLES CHARTS 7 2 14 11 8 BLANK ...