Application Examples
79
Assuming that the same requirements in the example above are present, the following
commands should be sent to the 2553/ 2553E to program the bank for the required data.
BANK0=VOLTS[1:40]/AMPS[1:40];READBANK=0<NL>
UPDATE0=50<NL>
The user should then program the 2553/ 2553E to assert the IEEE488.1 interface SRQ
line whenever the bank is updated by sending the following command.
STATUS=4<NL>
The application should be programmed to detect the assertion of the SRQ line and
perform a serial poll of the 2553/ 2553E to determine if it is the cause. Since the 2553/
2553E has only been programmed to assert this line when the bank is updated, there is no
need to actually check the response byte, in more typical applications this would be
performed since there would be other allowed causes (e.g., overload detection). When
the interrupt occurs the application simply reads the newly updated set of measurement
results (voltage and current harmonics in this example) from the 2553/ 2553E. No
command to the 2553/ 2553E is needed to perform this. The SRQ Status Byte is
automatically cleared when the serial poll takes place, in some cases it may be required to
program the application to perform the serial poll. The user should check the
documentation for the particular controller and software being used. Some packages
automatically perform the serial poll.
Changing the Configuration of the 2553/ 2553E
In rare circumstances, it may be required to reconfigure measurements in the 2553/
2553E after the initial configuration that was performed when the application was started.
Following any change to the measurement configuration of the 2553/ 2553E, or sending
the MEASURE=START<NL> or MEASURE=1<NL> commands, the 2553/ 2553E will
stop all measurements momentarily, clear all previous measurement results, and then
restart measurements using the new configuration. Prior to the completion of the first
internal measurement cycle, measurement results are not available and will be returned as
exactly zero. Typically this is a period of approximately 4 cycles of the applied voltage
waveform or 10ms (whichever is longer), this may be longer for harmonics and
frequency data, and shorter for peak measurements.
The user may wish to detect exactly zero measurement results and discard them
following reconfiguring measurements, or starting measurements using the MEASURE
command.
Synchronizing Results to Input Changes
To achieve the fastest possible measurement of a changed input signal level, it may be
beneficial to synchronize the 2553/ 2553E when it is known that a change in input has
occurred. An example of this is when line input is first applied to the load under the
control of the application.
Summary of Contents for Xitron 2553
Page 1: ...IEEE488 COMMAND GUIDE 2553 2553E Three Phase Power Analyser ...
Page 2: ......
Page 10: ...10 2553 2553E Command Guide ...
Page 38: ...38 2553 2553E Command Guide ...