Commissioning must be carried out by the IT expert or
system integrator.
1.
Switch on the heat generator.
2.
Switch on the power supply for the gateway.
3.
Check the status of the LED for standard mode
after switching on: See the following table.
If the LED indicators do not match the table, check
the connections: See overview on page 13.
LED indica-
tors
Status of the LED for standard
mode
SYS
Green
RUN
Green
I/O
Green
MS
Off
NS
Off
U1
Green
U2 - U6
Off
BT
Green
Note
If the LED lights up red or yellow, a
BACnet-specific error is present.
Clarification with system integrator
is required
4.
For further commissioning steps, see the "WAGO
BACnet Automation Gateway commissioning man-
ual" at
Note
CAN ID window defined for the LAG devices (77). All
LAG devices must be arranged in this address space,
otherwise they cannot be made available to the BMS.
Commissioning and adjustment
Commissioning the gateway
6175460