background image

12

Route pipes so that complete ventilation is ensured.
Install an air separator in the solar flow upstream of
the DHW cylinder.

Note

An air separator is integrated into the flow line of the
Solar-Divicon (see diagram).

Generally, copper lines in solar circuits are brazed or
joined by press fittings.
Soft solder could be weakened, particularly near the
collectors, due to the maximum temperatures occur-
ring there. Metal seal connections, locking ring fit-
tings or Viessmann plug-in connections with double
O-rings are the most suitable.
If other seals such as flat gaskets are used, ade-
quate glycol, pressure and temperature stability must
be guaranteed by the manufacturer.

Make all connections pressure and temperature
resistant (observe the maximum stagnation tempera-
ture of the collector).
Never use:

Teflon (inadequate glycol resistance)

Hemp connections (insufficiently gas-tight)

Equip the system to EN 12975 with an expansion
vessel, safety valve and circulation pump.

The expansion vessel must be approved to DIN
4807.
The diaphragms and seals of the expansion vessel
and safety valve must be suitable for the heat trans-
fer medium.

To calculate the pre-charge pressure, see the
"Vitosol" service instructions.

For operation without a Solar-Divicon, use only
safety valves that meet the following conditions:

Designed for 120 °C and up to 6 bar (0.6 MPa)

Letter ID "S" (solar) in the component identification

P

O

A

K

M

N

R

U

L

G

B

C

H

E

F

D

C

B

M

L

T

S

Fig. 7

A

Solar-Divicon

B

Shut-off valves

C

Non-return valves

D

Solar circuit pump

E

Air separator

F

Shut-off valve (adjusting screw above flow indica-
tor 

H

)

G

Drain valve

H

Flow indicator

K

Fill valve

L

Stagnation heat sink

M

Expansion vessel

N

Drip pan

O

Collector

R

DHW cylinder

S

Cylinder temperature sensor

T

Collector temperature sensor

U

Solar control unit

 

Installation

 (cont.)

5727 904 GB

Summary of Contents for SH

Page 1: ...Installation instructions for contractors VIESMANN Vitosol F Type SV and SH Flat plate collector for elevated installation VITOSOL F 5727 904 GB 10 2015 Dispose after installation ...

Page 2: ...qualified electrician Regulations to be observed National installation regulations Statutory regulations for the prevention of accidents Statutory regulations for the protection of the envi ronment Codes of practice of the relevant trade associations All relevant safety regulations as defined by DIN EN DVGW VDE and locally applicable standards a ÖNORM EN and ÖVE c SEV SUVA SVTI SWKI and SVGW Worki...

Page 3: ...culating collector row clearance z 7 Installation information 8 3 Installation sequence Installing the collector supports 9 Installing the collector 9 Fitting the connection set and collector temperature sensor 10 Installation 11 Commissioning 13 Index 5727 904 GB ...

Page 4: ...w component or In conjunction with a tool Clean the sur face Dispose of component correctly Dispose of component at a suitable collec tion point Do not dispose of component in domestic waste Intended use The collectors provide central heating backup and solar backup for DHW heating They are only intended to be installed and operated in sealed systems that comply with EN 12976 and EN 12977 with due...

Page 5: ... observe the installation instructions Failure to observe these instructions can change functions endanger life and limb of the user or third parties and will result in an exclusion of liability Incorrect usage also applies if components in the sys tem are modified from their intended use e g through direct DHW heating in the collector Adhere to statutory regulations especially concerning the hygi...

Page 6: ...or Vitosol F types SV and SH 6 4 2 3 5 8 7 1 9 1 5 7 5 1 5 7 5 1 SV 60 Fig 1 1 Collector support with footplates 2 Washer 7 8 4 mm 3 Hexagon nut M 8 4 Hexagon bolt M 8 x 20 5 Retaining bracket 6 Clamping bracket 7 Joining plate 8 Cross brace 9 Hexagon bolt M 8 x 25 Components 5727 904 GB ...

Page 7: ... angled 7 22 mm 90 qZ Support sleeve Sensor well set comprising qZ Support sleeve qU Locking ring fitting tee 7 22 mm qI Sensor well qO Strain relief fitting wP Thermal insulation Calculating collector row clearance z When installing several collectors in series maintain clearance z to prevent undesirable shading z β α α Fig 3 z Collector row clearance α Collector angle of inclination β Angle of t...

Page 8: ...the maximum load and distance from the edge of the roof for the on site substructure to DIN 1055 Installation on concrete slabs A see fig 4 Remove any gravel or similar from the installation area cover the surface with protective building mats and position support slabs on top of these mats Installation on steel beams B see fig 4 Install the on site substructure at right angles to and horizontally...

Page 9: ... 2200 1838 998 910 760 x mm 597 597 597 1921 1921 1921 y mm 480 480 480 480 480 480 Installing the collector Note on collector position The side with the type plate must be on the outside of the first and last collector If just 1 collector is used fit the pipework at the side opposite the type plate side Please note The connection pipes must be free of any signs of damage Lubricate O rings only wi...

Page 10: ...king ring fitting All pipes must be cut at right angles and deburred Push the union nut and the locking ring onto the pipe and lightly lubricate the threads with oil Push the pipe into the locking ring fitting as far as it will go Initially tighten union nut by hand then tighten with an open ended spanner by a further revolution Please note Connection pipes and plugs must not display any damage Lu...

Page 11: ...ed with heat transfer medium immediately after installation Protect collectors from insolation by covering them up Installation Please note Incorrect installation can lead to collector dam age Use only gunmetal or brass fittings and copper pipes for the installation Never step on collectors Never solder on or near the collectors Fitting the connection set and collector cont 5727 904 GB ...

Page 12: ...e glycol resistance Hemp connections insufficiently gas tight Equip the system to EN 12975 with an expansion vessel safety valve and circulation pump The expansion vessel must be approved to DIN 4807 The diaphragms and seals of the expansion vessel and safety valve must be suitable for the heat trans fer medium To calculate the pre charge pressure see the Vitosol service instructions For operation...

Page 13: ...13 For commissioning the solar thermal system see the Vitosol service instructions Commissioning 5727 904 GB ...

Page 14: ...14 5727 904 GB ...

Page 15: ...15 5727 904 GB ...

Page 16: ...hropshire TF1 7YP GB Telephone 44 1952 675000 Fax 44 1952 675040 E mail info uk viessmann com Viessmann Werke GmbH Co KG D 35107 Allendorf Telephone 49 6452 70 0 Fax 49 6452 70 2780 www viessmann com 5727 904 GB Subject to technical modifications ...