VALVE/TRIM INSTALLATION
1.
Make sure the trim drawings match system requirements.
2.
Remove all plastic caps and foam spacers from the valve.
3.
For valves installed with a Series 746 Dry Accelerator:
3a.
Make sure the Series 746 Dry Accelerator is installed on
the Series 753-A Dry Actuator, as shown in the drawing below.
The end with the vent seal "button" must be installed toward the
dry actuator.
IMPORTANT SETTINGS
System supervisory switches are required for dry systems.
These switches must be set to the notes below.
1.
Wire the air supervisory switches to activate a low-pres-
sure alarm signal.
NOTE:
The authority having jurisdiction may
also require a high-pressure alarm.
2.
Set the air supervisory switches to activate at 0,3 Bar be-
low the minimum air pressure required.
3.
Wire the alarm pressure switch to activate a water flow
alarm.
4.
Set the alarm pressure switch to activate on a pressure
rise of 0,3 – 0,6 Bar.
HYDROSTATIC TESTING
The Victaulic Series 756 European Dry Valve is manufactured
and listed for a maximum working pressure of 16 Bar and is fac-
tory tested to 41 Bar. The station can be hydrostatically tested to
14 Bar and/or 3,5 Bar above the normal water supply pressure
(2-hour limited time period) for acceptance by the authority hav-
ing jurisdiction.
CAUTION
• Make sure foam spacers are removed before
attempting to install the valve.
Failure to follow this instruction could cause
improper valve operation, resulting in serious
personal injury and/or property damage.
WARNING
• If air testing is required, DO NOT exceed 3,5
Bar air pressure.
Failure to follow this instruction could result in
serious personal injury, property damage, and/