10
NOTE
: The default IP address of an Enterprise controller is 192.168.0.250. If you changed
this in previous steps then enter the new address here.
4. At the Login page enter the
User name
“admin.”
5. Enter
the
Password
“admin.”
6. Click
Go
. The security application will now display.
7. Select
Setup : System Maintenance : Restore System
.
8. Click the link provided to upload the backup you previously made. Browse to the location of
the system backup file and click
Save
. The backup should now appear on the
Restore
System
page.
9. Click the button in the
Restore?
column next to the backup you wish to restore.
10. Click
Restore Now
.
11. When the system restore has completed you will be logged out.
Login and Swap the Unique Identifiers of the removed and newly installed Nodes
1. Log back in to the Enterprise controller.
2. Select
Setup : Site Settings : Network Nodes
.
3. Select from the
Name
drop-down the node which you removed.
4. Click
the
Commands
tab.
5. Click
the
Swap
button.
6. In the dialog box select from the drop-down the newly installed node.
NOTE
: If other nodes are powered you may need to know the Unique identifier for this new
node to make the correct selection. You can use nnconfig.exe to get this UID.
7. Click
Save
and confirm the swap in the popup.
NOTE
: Since resources (inputs, outputs, readers, etc.) are specific to a node unique
identifier, the Swap you performed in this procedure has reassigned the old node’s resources
to the new node.
8. Select
Setup : Site Settings : Network Nodes
.
9. Select from the
Name
drop-down the old node that you previously removed.
10. Click
Delete
.
NOTE
: This node is no longer in the network and deleting it will help avoid confusion.
Enable and connect remaining nodes to the Enterprise Controller
1. Select
Setup : Site Settings : Network Nodes
.
2. Select a node from the
Name
drop-down.
3. Click
the
Enabled
box and make any needed changes to the node’s settings.
4. Click
Save
.
5. Repeat steps 2, 3, and 4 for each node in the system.
6. Select
Setup : Site Settings : Network Controller
.
7. Check that the nodes are now connected to the Enterprise controller. Each node should
appear in green with the word
Connected
.
Summary of Contents for SMS Enterprise
Page 2: ......